First DT+RPC chambers installation round in the UX5 cavern
DT+RPC packages corresponding to sectors 1 and 7 of the barrel region cannot be installed on surface, since the lowering gantry from SX5 to UX5 uses their gaps to hold the wheels. Therefore this installation has to be carried out in the cavern. These pictures illustrate the first installation round...
Autor principal: | |
---|---|
Publicado: |
2007
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/1019185 |
Sumario: | DT+RPC packages corresponding to sectors 1 and 7 of the barrel region cannot be installed on surface, since the lowering gantry from SX5 to UX5 uses their gaps to hold the wheels. Therefore this installation has to be carried out in the cavern. These pictures illustrate the first installation round on YB+2 right after the lowering. A total of 8 chambers were successfully installed in 2 days. |
---|