LHC Collimation System Hardware Commissioning
The stored energy and intensity of the LHC beam exceed the damage level of the machine and the quench level of the magnets by far. Therefore a robust and reliable collimation system is required which prevents the quenching of the magnets during regular operation and protects the accelerator componen...
Autores principales: | Weiler, Th, Aberle, O, Assmann, Ralph Wolfgang, Chamizo, R, Kadi, Y, Lettry, Jacques, Losito, R, Redaelli, S |
---|---|
Lenguaje: | eng |
Publicado: |
2007
|
Materias: | |
Acceso en línea: | https://dx.doi.org/10.1109/PAC.2007.4440844 http://cds.cern.ch/record/1058823 |
Ejemplares similares
-
Beam Commissioning Plan For LHC Collimation
por: Bracco, C, et al.
Publicado: (2009) -
LHC collimation efficiency during commissioning
por: Assmann, R W, et al.
Publicado: (2006) -
LHC Aperture and Commissioning of the Collimation System
por: Redaelli, S, et al.
Publicado: (2005) -
Scenarios for Beam Commissioning of the LHC collimation system
por: Bracco, C, et al.
Publicado: (2007) -
BEAM COMMISSIONING PLAN FOR LHC COLLIMATION
por: Bracco, C, et al.
Publicado: (2009)