Installation and Hardware commissioning of the Multi-Turn extraction at the CERN proton synchrotron

The implementation of the new Multi-Turn Extraction (MTE) at the CERN Proton Synchrotron required major hardware changes for the nearly 50-year old accelerator. The installation of new Pulse Forming Networks (PFN) and refurbished kicker magnets for the extraction, new sextupole and octupole magnets,...

Descripción completa

Detalles Bibliográficos
Autores principales: Gilardoni, S, Allard, D, Barnes, M, Berrig, O, Beuret, A, Bodart, D, Bourquin, P, Brown, R, Caccioppoli, M, Caspers, Friedhelm, Cravero, JM, De Almeida Martins, C, Dehavay, C, Dobers, T, Dupont, M, Favre, G, Fowler, T, Franchi, A, Giovannozzi, M, Hansen, J, Karppinen, M, Lacroix, C, Mahner, E, Mertens, V, Monteiro, JL, Noulibos, R, Page, E, Principe, R, Rossi, C, Sermeus, L, Steerenberg, R, Vandoni, G, Villiger, G, Zickler, T
Lenguaje:eng
Publicado: 2009
Materias:
Acceso en línea:http://cds.cern.ch/record/1227219
Descripción
Sumario:The implementation of the new Multi-Turn Extraction (MTE) at the CERN Proton Synchrotron required major hardware changes for the nearly 50-year old accelerator. The installation of new Pulse Forming Networks (PFN) and refurbished kicker magnets for the extraction, new sextupole and octupole magnets, new power converters, together with an in-depth review of the machine aperture leading to the design of new vacuum chambers was required. As a result, a heavy programme of interventions had to be scheduled during the winter shut-down 2007-8. The newly installed hardware and its commissioning is presented and discussed in details.