New protection scheme and pressure relief-valve staging of the LHC insulation vacuum enclosure following the 19th September 2008 incident
This note defines the new protection scheme and the pressure relief valve staging of the LHC insulation vacuum enclosure which has to be implemented following the 19th September 2008 incident in the Sector 3-4. This note covers all the equipment located in the arcs, dispersion suppressors, matching...
Autores principales: | , , , |
---|---|
Lenguaje: | eng |
Publicado: |
2010
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/1316475 |
_version_ | 1780921396101120000 |
---|---|
author | Cruikshank, P Parma, V Perin, A Tavian, L |
author_facet | Cruikshank, P Parma, V Perin, A Tavian, L |
author_sort | Cruikshank, P |
collection | CERN |
description | This note defines the new protection scheme and the pressure relief valve staging of the LHC insulation vacuum enclosure which has to be implemented following the 19th September 2008 incident in the Sector 3-4. This note covers all the equipment located in the arcs, dispersion suppressors, matching sections and inner-triplets, including the QRL cryogenic line. As part of the machine will not be consolidated until the long shutdown scheduled after the first LHC operation years, a temporary protection scheme is also defined allowing a safe LHC operation at reduced beam energy. |
id | cern-1316475 |
institution | Organización Europea para la Investigación Nuclear |
language | eng |
publishDate | 2010 |
record_format | invenio |
spelling | cern-13164752019-09-30T06:29:59Zhttp://cds.cern.ch/record/1316475engCruikshank, PParma, VPerin, ATavian, LNew protection scheme and pressure relief-valve staging of the LHC insulation vacuum enclosure following the 19th September 2008 incidentAccelerators and Storage RingsThis note defines the new protection scheme and the pressure relief valve staging of the LHC insulation vacuum enclosure which has to be implemented following the 19th September 2008 incident in the Sector 3-4. This note covers all the equipment located in the arcs, dispersion suppressors, matching sections and inner-triplets, including the QRL cryogenic line. As part of the machine will not be consolidated until the long shutdown scheduled after the first LHC operation years, a temporary protection scheme is also defined allowing a safe LHC operation at reduced beam energy.CERN-ATS-Note-2010-057 TECHoai:cds.cern.ch:13164752010-12-01 |
spellingShingle | Accelerators and Storage Rings Cruikshank, P Parma, V Perin, A Tavian, L New protection scheme and pressure relief-valve staging of the LHC insulation vacuum enclosure following the 19th September 2008 incident |
title | New protection scheme and pressure relief-valve staging of the LHC insulation vacuum enclosure following the 19th September 2008 incident |
title_full | New protection scheme and pressure relief-valve staging of the LHC insulation vacuum enclosure following the 19th September 2008 incident |
title_fullStr | New protection scheme and pressure relief-valve staging of the LHC insulation vacuum enclosure following the 19th September 2008 incident |
title_full_unstemmed | New protection scheme and pressure relief-valve staging of the LHC insulation vacuum enclosure following the 19th September 2008 incident |
title_short | New protection scheme and pressure relief-valve staging of the LHC insulation vacuum enclosure following the 19th September 2008 incident |
title_sort | new protection scheme and pressure relief-valve staging of the lhc insulation vacuum enclosure following the 19th september 2008 incident |
topic | Accelerators and Storage Rings |
url | http://cds.cern.ch/record/1316475 |
work_keys_str_mv | AT cruikshankp newprotectionschemeandpressurereliefvalvestagingofthelhcinsulationvacuumenclosurefollowingthe19thseptember2008incident AT parmav newprotectionschemeandpressurereliefvalvestagingofthelhcinsulationvacuumenclosurefollowingthe19thseptember2008incident AT perina newprotectionschemeandpressurereliefvalvestagingofthelhcinsulationvacuumenclosurefollowingthe19thseptember2008incident AT tavianl newprotectionschemeandpressurereliefvalvestagingofthelhcinsulationvacuumenclosurefollowingthe19thseptember2008incident |