LS1 general planning and strategy for the LHC, LHC injectors

The goal of Long Shutdown 1 (LS1) is to perform the full maintenance of equipment, and the necessary consolidation and upgrade activities in order to ensure reliable LHC operation at nominal performance from mid 2014. LS1 not only concerns LHC but also its injectors. To ensure resources will be avai...

Descripción completa

Detalles Bibliográficos
Autor principal: Foraz, K
Lenguaje:eng
Publicado: CERN 2012
Materias:
Acceso en línea:https://dx.doi.org/10.5170/CERN-2012-006.212
http://cds.cern.ch/record/1492974
_version_ 1780926470038749184
author Foraz, K
author_facet Foraz, K
author_sort Foraz, K
collection CERN
description The goal of Long Shutdown 1 (LS1) is to perform the full maintenance of equipment, and the necessary consolidation and upgrade activities in order to ensure reliable LHC operation at nominal performance from mid 2014. LS1 not only concerns LHC but also its injectors. To ensure resources will be available an analysis is in progress to detect conflict/overload and decide what is compulsary, what we can afford, and what can be postponed to LS2. The strategy, time key drivers, constraints, and draft schedule will be presented here.
id cern-1492974
institution Organización Europea para la Investigación Nuclear
language eng
publishDate 2012
publisher CERN
record_format invenio
spelling cern-14929742022-08-10T20:28:36Zdoi:10.5170/CERN-2012-006.212http://cds.cern.ch/record/1492974engForaz, KLS1 general planning and strategy for the LHC, LHC injectorsAccelerators and Storage RingsThe goal of Long Shutdown 1 (LS1) is to perform the full maintenance of equipment, and the necessary consolidation and upgrade activities in order to ensure reliable LHC operation at nominal performance from mid 2014. LS1 not only concerns LHC but also its injectors. To ensure resources will be available an analysis is in progress to detect conflict/overload and decide what is compulsary, what we can afford, and what can be postponed to LS2. The strategy, time key drivers, constraints, and draft schedule will be presented here.CERNoai:cds.cern.ch:14929742012
spellingShingle Accelerators and Storage Rings
Foraz, K
LS1 general planning and strategy for the LHC, LHC injectors
title LS1 general planning and strategy for the LHC, LHC injectors
title_full LS1 general planning and strategy for the LHC, LHC injectors
title_fullStr LS1 general planning and strategy for the LHC, LHC injectors
title_full_unstemmed LS1 general planning and strategy for the LHC, LHC injectors
title_short LS1 general planning and strategy for the LHC, LHC injectors
title_sort ls1 general planning and strategy for the lhc, lhc injectors
topic Accelerators and Storage Rings
url https://dx.doi.org/10.5170/CERN-2012-006.212
http://cds.cern.ch/record/1492974
work_keys_str_mv AT forazk ls1generalplanningandstrategyforthelhclhcinjectors