Main Consolidations and Improvements of the Control System and Instrumentation for the LHC Cryogenics
Operation of the LHC during 2010 and 2011 with 3.5 TeV beam energy and luminosity up to 3.65x1033 cm-2 s-1, led to radiation-induced failures of micro-electronic devices used in the cryogenic control system. Mitigating actions addressed equipment relocation and corrective patches on electronics and...
Autores principales: | , , , , , , , , , , , |
---|---|
Lenguaje: | eng |
Publicado: |
2013
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/1507612 |
Sumario: | Operation of the LHC during 2010 and 2011 with 3.5 TeV beam energy and luminosity up to 3.65x1033 cm-2 s-1, led to radiation-induced failures of micro-electronic devices used in the cryogenic control system. Mitigating actions addressed equipment relocation and corrective patches on electronics and software. Driven by the technical requirements and by feedback from the cryogenic operation team, numerous consolidations and improvements were implemented on-the-fly, enhancing availability and operability of the LHC cryogenics. Furthermore, additional diagnostic tools, test benches, technical procedures and trainings have been provided to strengthen first line support services. |
---|