Commissioning of the Linac4 RFQ at the 3 MeV test stand
Linac4, the future 160 MeV Hˉ injector to the CERN Proton Synchrotron Booster, is presently under construction at CERN as a first step of the planned upgrade of the LHC injectors. The low energy section of LINAC4, consisting of an ion source, a 352.2 MHz Radio Frequency Quadrupole (RFQ) and a choppe...
Autores principales: | , , , , , , , , , , , , , , , |
---|---|
Lenguaje: | eng |
Publicado: |
2013
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/1595497 |
_version_ | 1780931137760133120 |
---|---|
author | Rossi, C Arnaudon, L Bellodi, G Broere, J Brunner, O Lombardi, A M Balula, J M Yanez, P M Noirjean, J Pasquino, C Raich, U Roncarolo, F Vretenar, M Desmons, M France, A Piquet, O |
author_facet | Rossi, C Arnaudon, L Bellodi, G Broere, J Brunner, O Lombardi, A M Balula, J M Yanez, P M Noirjean, J Pasquino, C Raich, U Roncarolo, F Vretenar, M Desmons, M France, A Piquet, O |
author_sort | Rossi, C |
collection | CERN |
description | Linac4, the future 160 MeV Hˉ injector to the CERN Proton Synchrotron Booster, is presently under construction at CERN as a first step of the planned upgrade of the LHC injectors. The low energy section of LINAC4, consisting of an ion source, a 352.2 MHz Radio Frequency Quadrupole (RFQ) and a chopper line is being commissioned in a dedicated test stand before installation in its final position in the tunnel. The RFQ is designed to accelerate a 45 keV, 70 mA, Hˉ beam to 3 MeV, with an efficiency of 95% while preserving the transverse emittance. The RFQ, a four-vane structure 3 m in length, has been designed in collaboration with CEA/IRFU and is has been fabricated at the CERN workshop. The precise fabrication has allowed achieving a field flatness of 1%. The completion of the accelerating structure in September 2012 was followed by a complete series of bead-pull measurements and by high-power conditioning to the nominal power of 0.39 MW corresponding to a voltage of 78 kV across the 3 meters. Measurements with beam are taking place during the first half of 2013. |
id | cern-1595497 |
institution | Organización Europea para la Investigación Nuclear |
language | eng |
publishDate | 2013 |
record_format | invenio |
spelling | cern-15954972019-09-30T06:29:59Zhttp://cds.cern.ch/record/1595497engRossi, CArnaudon, LBellodi, GBroere, JBrunner, OLombardi, A MBalula, J MYanez, P MNoirjean, JPasquino, CRaich, URoncarolo, FVretenar, MDesmons, MFrance, APiquet, OCommissioning of the Linac4 RFQ at the 3 MeV test standAccelerators and Storage RingsLinac4, the future 160 MeV Hˉ injector to the CERN Proton Synchrotron Booster, is presently under construction at CERN as a first step of the planned upgrade of the LHC injectors. The low energy section of LINAC4, consisting of an ion source, a 352.2 MHz Radio Frequency Quadrupole (RFQ) and a chopper line is being commissioned in a dedicated test stand before installation in its final position in the tunnel. The RFQ is designed to accelerate a 45 keV, 70 mA, Hˉ beam to 3 MeV, with an efficiency of 95% while preserving the transverse emittance. The RFQ, a four-vane structure 3 m in length, has been designed in collaboration with CEA/IRFU and is has been fabricated at the CERN workshop. The precise fabrication has allowed achieving a field flatness of 1%. The completion of the accelerating structure in September 2012 was followed by a complete series of bead-pull measurements and by high-power conditioning to the nominal power of 0.39 MW corresponding to a voltage of 78 kV across the 3 meters. Measurements with beam are taking place during the first half of 2013.CERN-ACC-2013-0201oai:cds.cern.ch:15954972013-05-12 |
spellingShingle | Accelerators and Storage Rings Rossi, C Arnaudon, L Bellodi, G Broere, J Brunner, O Lombardi, A M Balula, J M Yanez, P M Noirjean, J Pasquino, C Raich, U Roncarolo, F Vretenar, M Desmons, M France, A Piquet, O Commissioning of the Linac4 RFQ at the 3 MeV test stand |
title | Commissioning of the Linac4 RFQ at the 3 MeV test stand |
title_full | Commissioning of the Linac4 RFQ at the 3 MeV test stand |
title_fullStr | Commissioning of the Linac4 RFQ at the 3 MeV test stand |
title_full_unstemmed | Commissioning of the Linac4 RFQ at the 3 MeV test stand |
title_short | Commissioning of the Linac4 RFQ at the 3 MeV test stand |
title_sort | commissioning of the linac4 rfq at the 3 mev test stand |
topic | Accelerators and Storage Rings |
url | http://cds.cern.ch/record/1595497 |
work_keys_str_mv | AT rossic commissioningofthelinac4rfqatthe3mevteststand AT arnaudonl commissioningofthelinac4rfqatthe3mevteststand AT bellodig commissioningofthelinac4rfqatthe3mevteststand AT broerej commissioningofthelinac4rfqatthe3mevteststand AT brunnero commissioningofthelinac4rfqatthe3mevteststand AT lombardiam commissioningofthelinac4rfqatthe3mevteststand AT balulajm commissioningofthelinac4rfqatthe3mevteststand AT yanezpm commissioningofthelinac4rfqatthe3mevteststand AT noirjeanj commissioningofthelinac4rfqatthe3mevteststand AT pasquinoc commissioningofthelinac4rfqatthe3mevteststand AT raichu commissioningofthelinac4rfqatthe3mevteststand AT roncarolof commissioningofthelinac4rfqatthe3mevteststand AT vretenarm commissioningofthelinac4rfqatthe3mevteststand AT desmonsm commissioningofthelinac4rfqatthe3mevteststand AT francea commissioningofthelinac4rfqatthe3mevteststand AT piqueto commissioningofthelinac4rfqatthe3mevteststand |