Status report for the Neutrino Platform NP05 (Baby MIND) experiment

Report outlining progress by the Baby MIND collaboration since the October 2015 SPSC committee meeting. The Baby-MIND proposal was approved as NP05 with a clear recommendation to focus the project on the timely delivery of the magnetized downstream muon spectrometer for the Wagasci project. The meas...

Descripción completa

Detalles Bibliográficos
Autor principal: Noah, E
Publicado: 2016
Materias:
Acceso en línea:http://cds.cern.ch/record/2145413
_version_ 1780950303902793728
author Noah, E
author_facet Noah, E
author_sort Noah, E
collection CERN
description Report outlining progress by the Baby MIND collaboration since the October 2015 SPSC committee meeting. The Baby-MIND proposal was approved as NP05 with a clear recommendation to focus the project on the timely delivery of the magnetized downstream muon spectrometer for the Wagasci project. The measures taken to fullfill these recommendations are summarized. The status of the magnet design and procurement; of the detector modules, procurement of scintillator and module mechanics design; the status of the electronics and DAQ; and finally simulations and analysis are desctribed. The project schedule and milestones, the plans for test beam and the request for the use of the T9 test area are presented.
id cern-2145413
institution Organización Europea para la Investigación Nuclear
publishDate 2016
record_format invenio
spelling cern-21454132019-09-30T06:29:59Zhttp://cds.cern.ch/record/2145413Noah, EStatus report for the Neutrino Platform NP05 (Baby MIND) experimentDetectors and Experimental TechniquesReport outlining progress by the Baby MIND collaboration since the October 2015 SPSC committee meeting. The Baby-MIND proposal was approved as NP05 with a clear recommendation to focus the project on the timely delivery of the magnetized downstream muon spectrometer for the Wagasci project. The measures taken to fullfill these recommendations are summarized. The status of the magnet design and procurement; of the detector modules, procurement of scintillator and module mechanics design; the status of the electronics and DAQ; and finally simulations and analysis are desctribed. The project schedule and milestones, the plans for test beam and the request for the use of the T9 test area are presented.CERN-SPSC-2016-020SPSC-SR-187oai:cds.cern.ch:21454132016-04-12
spellingShingle Detectors and Experimental Techniques
Noah, E
Status report for the Neutrino Platform NP05 (Baby MIND) experiment
title Status report for the Neutrino Platform NP05 (Baby MIND) experiment
title_full Status report for the Neutrino Platform NP05 (Baby MIND) experiment
title_fullStr Status report for the Neutrino Platform NP05 (Baby MIND) experiment
title_full_unstemmed Status report for the Neutrino Platform NP05 (Baby MIND) experiment
title_short Status report for the Neutrino Platform NP05 (Baby MIND) experiment
title_sort status report for the neutrino platform np05 (baby mind) experiment
topic Detectors and Experimental Techniques
url http://cds.cern.ch/record/2145413
work_keys_str_mv AT noahe statusreportfortheneutrinoplatformnp05babymindexperiment