Commissioning of DCS interfaces to front-end modules

This report contains all the work done during a 3-month internship within the team in charge of the ALICE detector control system at the European Organization for Nuclear Research (CERN). At the next upgrade of the ALICE detector at the end of the LHC RUN2, new temperature and humidity sensors must...

Descripción completa

Detalles Bibliográficos
Autor principal: Breton, Gaetan Ludovic
Lenguaje:eng
Publicado: 2018
Materias:
Acceso en línea:http://cds.cern.ch/record/2640192
Descripción
Sumario:This report contains all the work done during a 3-month internship within the team in charge of the ALICE detector control system at the European Organization for Nuclear Research (CERN). At the next upgrade of the ALICE detector at the end of the LHC RUN2, new temperature and humidity sensors must be installed, this report allows to select these sensors. This report also introduces you to a new tool that allows you to record sensor tests and retrieve them later.