TIDVG#5 mock-up assembly in BA5, dismantling and re installing beamline in SPS tunnel
Dismantling of beamline BA5 "decabling, dismantling and enlargement of tunnel in new beamline, cabling, rebuild LS5 beamline" 90% vacuum around SPS. Remove beam dump remove from BA1 to install new one in BA5. New beam dump on surface (test in b.899)
Autor principal: | |
---|---|
Publicado: |
2019
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/2677262 |
Sumario: | Dismantling of beamline BA5 "decabling, dismantling and enlargement of tunnel in new beamline, cabling, rebuild LS5 beamline" 90% vacuum around SPS. Remove beam dump remove from BA1 to install new one in BA5. New beam dump on surface (test in b.899) |
---|