TIDVG#5 mock-up assembly in BA5, dismantling and re installing beamline in SPS tunnel
Dismantling of beamline BA5 "decabling, dismantling and enlargement of tunnel in new beamline, cabling, rebuild LS5 beamline" 90% vacuum around SPS. Remove beam dump remove from BA1 to install new one in BA5. New beam dump on surface (test in b.899)