HiRadMat experiment installation for the first beam time run after LS2

Four different experiments (HRMT-52 BTV, HRMT-53 CHEFT, HRMT-54 BPM, HRMT-55 BLM3) were installed in the HiRadMat Facility for the first beam time run of this year after LS2. During HRMT-52 the performance of different beam screen materials for highly-focused, high-intensity beams were evaluated. No...

Descripción completa

Detalles Bibliográficos
Autores principales: Traczyk, Piotr, Simon, Pascal, Hertzog, Samuel Joseph
Publicado: 2021
Materias:
LS2
Acceso en línea:http://cds.cern.ch/record/2778750
Descripción
Sumario:Four different experiments (HRMT-52 BTV, HRMT-53 CHEFT, HRMT-54 BPM, HRMT-55 BLM3) were installed in the HiRadMat Facility for the first beam time run of this year after LS2. During HRMT-52 the performance of different beam screen materials for highly-focused, high-intensity beams were evaluated. Novel carbon nanotube wires were irradiated in HRMT-53 CHEFT for the next-generation of wirescanners. HRMT-54 BPM tested electro-optical and RF-based beam position monitor prototypes for the HiLumi upgrade of LHC. HRMT-55 BLM3 is using the mixed radiaton-field inside the HiRadMat Facility to calibrate production and prototype Beam Loss Monitors for LHC, SPS and various other facilities (ESS and FAIR). HiRadMat (or High-Radiation to Materials) is a users facility at CERN, designed to provide high-intensity pulsed beams to an irradiation area where material samples as well as accelerator component assemblies can be tested.