Chapter 5 Infrastructure consolidation

Constructed in 1963, Building 157 is 113 m long and 43 m wide at ground level. The roof is 21.8 m high at the central point above a skylight running longitudinally down its centre; it has a slope of 20% running down to the longitudinal façade summits at 15.6 m. The roof is 47.4 m wide as the longit...

Descripción completa

Detalles Bibliográficos
Autores principales: Burdelski, P, Dragoni, F, Grau, Silvia, Guillaume, J-C, Jaillet, D, Mcilwraith, S, Polenghi, M, Sanchez, E
Lenguaje:eng
Publicado: 2021
Materias:
Acceso en línea:https://dx.doi.org/10.23731/CYRM-2021-004.89
http://cds.cern.ch/record/2797855
_version_ 1780972444991881216
author Burdelski, P
Dragoni, F
Grau, Silvia
Guillaume, J-C
Jaillet, D
Mcilwraith, S
Polenghi, M
Sanchez, E
author_facet Burdelski, P
Dragoni, F
Grau, Silvia
Guillaume, J-C
Jaillet, D
Mcilwraith, S
Polenghi, M
Sanchez, E
author_sort Burdelski, P
collection CERN
description Constructed in 1963, Building 157 is 113 m long and 43 m wide at ground level. The roof is 21.8 m high at the central point above a skylight running longitudinally down its centre; it has a slope of 20% running down to the longitudinal façade summits at 15.6 m. The roof is 47.4 m wide as the longitudinal façades include wings protruding 2.2 m from a height of 7.5 m to the summits, running the entire length of the building. The longitudinal façades are made up of a variety of materials (masonry, wood agglomerate, fibro-cement, and glass). The end walls are made of reinforced concrete (Northwest wall) or wood agglomerate (Southeast wall). The East Hall is now 55 years old and many facets of the building envelope are in an unacceptable state. There are dilapidated and unsafe materials forming and falling from the envelope of the building. The uninsulated envelope does not conform to current building energy-management requirements, resulting in disproportional thermal losses and hence financial losses due to heating requirements. The envelope renovation project has two principal objectives with a number of specific objectives. – ‘To improve the safety and comfort in the building by replacing the existing envelope’. Removing the dilapidate asbestos-containing ceiling panels. Removing existing poorly fixed, single-glazed windows with asbestos containing joints. Removing existing uninsulated fibro-cement façade panels. Eradicating the water infiltrations coming from the roof. – To ensure a synergy with the consolidation of the façade of the attached Building 156. As such, the entire envelope was studied in an attempt to create a safe environment, optimizing energy savings, responding to modern building codes, and respect an aesthetic liaison with Building 156.    
id cern-2797855
institution Organización Europea para la Investigación Nuclear
language eng
publishDate 2021
record_format invenio
spelling cern-27978552021-12-14T20:19:10Zdoi:10.23731/CYRM-2021-004.89http://cds.cern.ch/record/2797855engBurdelski, PDragoni, FGrau, SilviaGuillaume, J-CJaillet, DMcilwraith, SPolenghi, MSanchez, EChapter 5 Infrastructure consolidationAccelerators and Storage RingsConstructed in 1963, Building 157 is 113 m long and 43 m wide at ground level. The roof is 21.8 m high at the central point above a skylight running longitudinally down its centre; it has a slope of 20% running down to the longitudinal façade summits at 15.6 m. The roof is 47.4 m wide as the longitudinal façades include wings protruding 2.2 m from a height of 7.5 m to the summits, running the entire length of the building. The longitudinal façades are made up of a variety of materials (masonry, wood agglomerate, fibro-cement, and glass). The end walls are made of reinforced concrete (Northwest wall) or wood agglomerate (Southeast wall). The East Hall is now 55 years old and many facets of the building envelope are in an unacceptable state. There are dilapidated and unsafe materials forming and falling from the envelope of the building. The uninsulated envelope does not conform to current building energy-management requirements, resulting in disproportional thermal losses and hence financial losses due to heating requirements. The envelope renovation project has two principal objectives with a number of specific objectives. – ‘To improve the safety and comfort in the building by replacing the existing envelope’. Removing the dilapidate asbestos-containing ceiling panels. Removing existing poorly fixed, single-glazed windows with asbestos containing joints. Removing existing uninsulated fibro-cement façade panels. Eradicating the water infiltrations coming from the roof. – To ensure a synergy with the consolidation of the façade of the attached Building 156. As such, the entire envelope was studied in an attempt to create a safe environment, optimizing energy savings, responding to modern building codes, and respect an aesthetic liaison with Building 156.    oai:cds.cern.ch:27978552021
spellingShingle Accelerators and Storage Rings
Burdelski, P
Dragoni, F
Grau, Silvia
Guillaume, J-C
Jaillet, D
Mcilwraith, S
Polenghi, M
Sanchez, E
Chapter 5 Infrastructure consolidation
title Chapter 5 Infrastructure consolidation
title_full Chapter 5 Infrastructure consolidation
title_fullStr Chapter 5 Infrastructure consolidation
title_full_unstemmed Chapter 5 Infrastructure consolidation
title_short Chapter 5 Infrastructure consolidation
title_sort chapter 5 infrastructure consolidation
topic Accelerators and Storage Rings
url https://dx.doi.org/10.23731/CYRM-2021-004.89
http://cds.cern.ch/record/2797855
work_keys_str_mv AT burdelskip chapter5infrastructureconsolidation
AT dragonif chapter5infrastructureconsolidation
AT grausilvia chapter5infrastructureconsolidation
AT guillaumejc chapter5infrastructureconsolidation
AT jailletd chapter5infrastructureconsolidation
AT mcilwraiths chapter5infrastructureconsolidation
AT polenghim chapter5infrastructureconsolidation
AT sancheze chapter5infrastructureconsolidation