LHC Vacuum Supervisory Application for Run 3
The LHC Vacuum Supervisory Control and Data Acquisition application has been upgraded to fulfil the new requirements of Long Shutdown 2 and Run 3. The number of datapoint elements has been increased from 700k to 1.5M, which constitutes a challenge in terms of scalability. The new configuration of pu...
Autores principales: | , , , , , , , , , |
---|---|
Lenguaje: | eng |
Publicado: |
2022
|
Materias: | |
Acceso en línea: | https://dx.doi.org/10.18429/JACoW-ICALEPCS2021-TUPV031 http://cds.cern.ch/record/2809473 |
Sumario: | The LHC Vacuum Supervisory Control and Data Acquisition application has been upgraded to fulfil the new requirements of Long Shutdown 2 and Run 3. The number of datapoint elements has been increased from 700k to 1.5M, which constitutes a challenge in terms of scalability. The new configuration of pumping station control hardware has led to an increase in the number of permanently connected PLCs from 150 to almost 300. A new concept has been developed and deployed, in which the PLC configuration is updated online. The goals were to automate, and to speed up periodic updates of the control system. Integrating of the wireless mobile equipment had led to the acquisition of expertise in dealing with temporary connections and dynamic insertion of device representation in the synoptic. Other new features include: the introduction of an innovative remote control and representation in synoptic panel of hardware interlocks, the development of a pre-configured notification system, and the integration of asset management into the user interface. |
---|