List of Works to be done during the Shut-down of the P.S. Machine from 27th December 1961 to 16th January 1962
Autor principal: | Gouiran, R |
---|---|
Lenguaje: | eng |
Publicado: |
1961
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/2829838 |
Ejemplares similares
-
List of work to be done during the September - October shut-down of the PS: 27th August - 23rd October 1962
por: Gouiran, R
Publicado: (1962) -
Works to be done during the May shut-down
por: Gouiran, R
Publicado: (1962) -
PS Coordination memorandum: PS Schedule December 1961 - January 1962 asuming North and South Hall bubble chambers can share beam
por: CERN. Geneva. Proton Synchrotron
Publicado: (1961) -
PS Coordination memorandum: PS Schedule December 1961 - January 1962 asuming North and South Hall bubble chambers can share beam
por: CERN. Geneva. Proton Synchrotron
Publicado: (1961) -
PS Coordination note: PS Schedule 10 - 17 July 1961 (Shut-down)
por: Von Dardel, G