Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors

The CERN LHC injector chain underwent a major upgrade during the Long Shutdown 2 (LS2) in the framework of the LHC Injectors Upgrade (LIU) project. After 2 years of installation work, the Proton Synchrotron (PS) was restarted in 2021 with the goal to achieve pre-LS2 beam quality by the end of 2021....

Descripción completa

Detalles Bibliográficos
Autores principales: Huschauer, Alexander, Coly, Marcel, Cotte, Denis, Damerau, Heiko, Delrieux, Marc, Dumont, Jean-Charles, Dutheil, Yann, Easton, Sandy, Fraser, Matthew, Hans, Oliver, Imesch, Gil, Joly, Sébastien, Lasheen, Alexandre, Lombard, Cedric, Maillet, Rodolphe, Mikulec, Bettina, Nonglaton, Jean-Michel, Sainz Perez, Sara, Salvant, Benoit, Suykerbuyk, Ronaldus, Tecker, Frank, Valera Teruel, Raul
Lenguaje:eng
Publicado: 2022
Materias:
Acceso en línea:https://dx.doi.org/10.18429/JACoW-IPAC2022-MOPOST006
http://cds.cern.ch/record/2845857
_version_ 1780976593186848768
author Huschauer, Alexander
Coly, Marcel
Cotte, Denis
Damerau, Heiko
Delrieux, Marc
Dumont, Jean-Charles
Dutheil, Yann
Easton, Sandy
Fraser, Matthew
Hans, Oliver
Imesch, Gil
Joly, Sébastien
Lasheen, Alexandre
Lombard, Cedric
Maillet, Rodolphe
Mikulec, Bettina
Nonglaton, Jean-Michel
Sainz Perez, Sara
Salvant, Benoit
Suykerbuyk, Ronaldus
Tecker, Frank
Valera Teruel, Raul
author_facet Huschauer, Alexander
Coly, Marcel
Cotte, Denis
Damerau, Heiko
Delrieux, Marc
Dumont, Jean-Charles
Dutheil, Yann
Easton, Sandy
Fraser, Matthew
Hans, Oliver
Imesch, Gil
Joly, Sébastien
Lasheen, Alexandre
Lombard, Cedric
Maillet, Rodolphe
Mikulec, Bettina
Nonglaton, Jean-Michel
Sainz Perez, Sara
Salvant, Benoit
Suykerbuyk, Ronaldus
Tecker, Frank
Valera Teruel, Raul
author_sort Huschauer, Alexander
collection CERN
description The CERN LHC injector chain underwent a major upgrade during the Long Shutdown 2 (LS2) in the framework of the LHC Injectors Upgrade (LIU) project. After 2 years of installation work, the Proton Synchrotron (PS) was restarted in 2021 with the goal to achieve pre-LS2 beam quality by the end of 2021. This contribution details the main beam commissioning milestones, difficulties encountered and lessons learned. The status of the fixed-target and LHC beams will be given and improvements in terms of performance, controls and tools will be described.
id cern-2845857
institution Organización Europea para la Investigación Nuclear
language eng
publishDate 2022
record_format invenio
spelling cern-28458572023-01-11T21:31:26Zdoi:10.18429/JACoW-IPAC2022-MOPOST006http://cds.cern.ch/record/2845857engHuschauer, AlexanderColy, MarcelCotte, DenisDamerau, HeikoDelrieux, MarcDumont, Jean-CharlesDutheil, YannEaston, SandyFraser, MatthewHans, OliverImesch, GilJoly, SébastienLasheen, AlexandreLombard, CedricMaillet, RodolpheMikulec, BettinaNonglaton, Jean-MichelSainz Perez, SaraSalvant, BenoitSuykerbuyk, RonaldusTecker, FrankValera Teruel, RaulBeam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC InjectorsAccelerators and Storage RingsThe CERN LHC injector chain underwent a major upgrade during the Long Shutdown 2 (LS2) in the framework of the LHC Injectors Upgrade (LIU) project. After 2 years of installation work, the Proton Synchrotron (PS) was restarted in 2021 with the goal to achieve pre-LS2 beam quality by the end of 2021. This contribution details the main beam commissioning milestones, difficulties encountered and lessons learned. The status of the fixed-target and LHC beams will be given and improvements in terms of performance, controls and tools will be described.oai:cds.cern.ch:28458572022
spellingShingle Accelerators and Storage Rings
Huschauer, Alexander
Coly, Marcel
Cotte, Denis
Damerau, Heiko
Delrieux, Marc
Dumont, Jean-Charles
Dutheil, Yann
Easton, Sandy
Fraser, Matthew
Hans, Oliver
Imesch, Gil
Joly, Sébastien
Lasheen, Alexandre
Lombard, Cedric
Maillet, Rodolphe
Mikulec, Bettina
Nonglaton, Jean-Michel
Sainz Perez, Sara
Salvant, Benoit
Suykerbuyk, Ronaldus
Tecker, Frank
Valera Teruel, Raul
Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors
title Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors
title_full Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors
title_fullStr Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors
title_full_unstemmed Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors
title_short Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors
title_sort beam commissioning and optimisation in the cern proton synchrotron after the upgrade of the lhc injectors
topic Accelerators and Storage Rings
url https://dx.doi.org/10.18429/JACoW-IPAC2022-MOPOST006
http://cds.cern.ch/record/2845857
work_keys_str_mv AT huschaueralexander beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT colymarcel beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT cottedenis beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT damerauheiko beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT delrieuxmarc beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT dumontjeancharles beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT dutheilyann beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT eastonsandy beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT frasermatthew beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT hansoliver beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT imeschgil beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT jolysebastien beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT lasheenalexandre beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT lombardcedric beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT mailletrodolphe beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT mikulecbettina beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT nonglatonjeanmichel beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT sainzperezsara beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT salvantbenoit beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT suykerbuykronaldus beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT teckerfrank beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors
AT valerateruelraul beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors