Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors
The CERN LHC injector chain underwent a major upgrade during the Long Shutdown 2 (LS2) in the framework of the LHC Injectors Upgrade (LIU) project. After 2 years of installation work, the Proton Synchrotron (PS) was restarted in 2021 with the goal to achieve pre-LS2 beam quality by the end of 2021....
Autores principales: | , , , , , , , , , , , , , , , , , , , , , |
---|---|
Lenguaje: | eng |
Publicado: |
2022
|
Materias: | |
Acceso en línea: | https://dx.doi.org/10.18429/JACoW-IPAC2022-MOPOST006 http://cds.cern.ch/record/2845857 |
_version_ | 1780976593186848768 |
---|---|
author | Huschauer, Alexander Coly, Marcel Cotte, Denis Damerau, Heiko Delrieux, Marc Dumont, Jean-Charles Dutheil, Yann Easton, Sandy Fraser, Matthew Hans, Oliver Imesch, Gil Joly, Sébastien Lasheen, Alexandre Lombard, Cedric Maillet, Rodolphe Mikulec, Bettina Nonglaton, Jean-Michel Sainz Perez, Sara Salvant, Benoit Suykerbuyk, Ronaldus Tecker, Frank Valera Teruel, Raul |
author_facet | Huschauer, Alexander Coly, Marcel Cotte, Denis Damerau, Heiko Delrieux, Marc Dumont, Jean-Charles Dutheil, Yann Easton, Sandy Fraser, Matthew Hans, Oliver Imesch, Gil Joly, Sébastien Lasheen, Alexandre Lombard, Cedric Maillet, Rodolphe Mikulec, Bettina Nonglaton, Jean-Michel Sainz Perez, Sara Salvant, Benoit Suykerbuyk, Ronaldus Tecker, Frank Valera Teruel, Raul |
author_sort | Huschauer, Alexander |
collection | CERN |
description | The CERN LHC injector chain underwent a major upgrade during the Long Shutdown 2 (LS2) in the framework of the LHC Injectors Upgrade (LIU) project. After 2 years of installation work, the Proton Synchrotron (PS) was restarted in 2021 with the goal to achieve pre-LS2 beam quality by the end of 2021. This contribution details the main beam commissioning milestones, difficulties encountered and lessons learned. The status of the fixed-target and LHC beams will be given and improvements in terms of performance, controls and tools will be described. |
id | cern-2845857 |
institution | Organización Europea para la Investigación Nuclear |
language | eng |
publishDate | 2022 |
record_format | invenio |
spelling | cern-28458572023-01-11T21:31:26Zdoi:10.18429/JACoW-IPAC2022-MOPOST006http://cds.cern.ch/record/2845857engHuschauer, AlexanderColy, MarcelCotte, DenisDamerau, HeikoDelrieux, MarcDumont, Jean-CharlesDutheil, YannEaston, SandyFraser, MatthewHans, OliverImesch, GilJoly, SébastienLasheen, AlexandreLombard, CedricMaillet, RodolpheMikulec, BettinaNonglaton, Jean-MichelSainz Perez, SaraSalvant, BenoitSuykerbuyk, RonaldusTecker, FrankValera Teruel, RaulBeam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC InjectorsAccelerators and Storage RingsThe CERN LHC injector chain underwent a major upgrade during the Long Shutdown 2 (LS2) in the framework of the LHC Injectors Upgrade (LIU) project. After 2 years of installation work, the Proton Synchrotron (PS) was restarted in 2021 with the goal to achieve pre-LS2 beam quality by the end of 2021. This contribution details the main beam commissioning milestones, difficulties encountered and lessons learned. The status of the fixed-target and LHC beams will be given and improvements in terms of performance, controls and tools will be described.oai:cds.cern.ch:28458572022 |
spellingShingle | Accelerators and Storage Rings Huschauer, Alexander Coly, Marcel Cotte, Denis Damerau, Heiko Delrieux, Marc Dumont, Jean-Charles Dutheil, Yann Easton, Sandy Fraser, Matthew Hans, Oliver Imesch, Gil Joly, Sébastien Lasheen, Alexandre Lombard, Cedric Maillet, Rodolphe Mikulec, Bettina Nonglaton, Jean-Michel Sainz Perez, Sara Salvant, Benoit Suykerbuyk, Ronaldus Tecker, Frank Valera Teruel, Raul Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors |
title | Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors |
title_full | Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors |
title_fullStr | Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors |
title_full_unstemmed | Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors |
title_short | Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors |
title_sort | beam commissioning and optimisation in the cern proton synchrotron after the upgrade of the lhc injectors |
topic | Accelerators and Storage Rings |
url | https://dx.doi.org/10.18429/JACoW-IPAC2022-MOPOST006 http://cds.cern.ch/record/2845857 |
work_keys_str_mv | AT huschaueralexander beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT colymarcel beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT cottedenis beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT damerauheiko beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT delrieuxmarc beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT dumontjeancharles beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT dutheilyann beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT eastonsandy beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT frasermatthew beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT hansoliver beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT imeschgil beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT jolysebastien beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT lasheenalexandre beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT lombardcedric beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT mailletrodolphe beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT mikulecbettina beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT nonglatonjeanmichel beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT sainzperezsara beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT salvantbenoit beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT suykerbuykronaldus beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT teckerfrank beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors AT valerateruelraul beamcommissioningandoptimisationinthecernprotonsynchrotronaftertheupgradeofthelhcinjectors |