Contract Management of LHC Civil Engineering at Point 5
Civil engineering work commenced in August 1998 at LEP Point 5 for the underground and surface works necessary to accommodate the CMS detector for the LHC project. The principal underground works consist of two parallel caverns, separated by a support pillar, two new shafts, a number of smaller conn...