October, 25th, 2000 First Barrel Ring with extension shaft ready for separation
The Ferris Wheel has served as a tool to build up the three-layered Barrel of the CMS return yoke. Now at the end of the assembly the barrel ring will be put on air pads and be pushed out.
Autor principal: | Hubert Gerwig |
---|---|
Publicado: |
2000
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/41795 |
Ejemplares similares
-
On september 17th, 1999 the first barrel ring of the CMS barrel yoke was finished. This event was celeberated by a CERN/CMS delegation and the local responsibles.
por: DWE Werksfoto Nr: 6.46305.528, et al.
Publicado: (1999) -
Big Barrel Yoke block after painting, ready for transport, weight 40 t
por: Franz Leher, DWE, et al.
Publicado: (2000) -
Start of Final Assembly of the CMS Barrel Yoke on schedule at P5 the 1st august, 2000. I
por: Hubert Gerwig, CERN/ EP-CMI
Publicado: (2000) -
Right and left support feet of the Central Barrel Yoke of the CMS Detector
por: Franz Leher, DWE, et al.
Publicado: (2000) -
Machining of casted steel Corner Piece of Barrel Yoke at ZDAS company in Czech Republic
por: Franz Leher, DWE, et al.
Publicado: (1999)