Cargando…
LHC Civil Engineering Construction Contracts: Cost Monitoring and Budget Forecasting
The Civil Engineering project for the LHC is estimated at 350 MCHF, of which about 316 MCHF is for the construction contracts. These contracts are based on a system of remeasurement whereby the consultant estimates the quantities required for the construction of each structure and the contractor com...
Autor principal: | Skelton, K |
---|---|
Lenguaje: | eng |
Publicado: |
2000
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/435816 |
Ejemplares similares
-
Organization and management of the LHC civil-engineering contracts
por: Watson, T
Publicado: (1999) -
The construction of the LHC: civil engineering highlights
por: Baldy, Jean-Luc, et al.
Publicado: (2009) -
The Use of Value Engineering Techniques in the LHC Civil Engineering Contracts
por: Watson, T
Publicado: (2000) -
Contract Management of LHC Civil Engineering at Point 5
por: Osborne, J A
Publicado: (1999) -
The role of CERN in the large construction contracts for LHC civil works
por: D'Aça-Castel-Branco, P
Publicado: (1998)