LHC Electrical Installations: Status Report
During 1999 the ST-EL group started detailed preparations for the electrical installations for the LHC. The areas of activity have been zone 18, access point 5 and the preparations around BA 4 and BA 7. Another activity performed during 1999 was the laying of the 18 kV cable link from LHC 6 to LHC 5...