Beam Dump TIDV #1 - Vacuum Failure of 17 Oct. 97

A vacuum leak on the internal beam dump TIDV precipitated its replacement in the LSS1 on Monday the 20th of October 1997, the SPS consequently being shut down for three days. The dump had fulfilled its design function since it was installed in the SPS at the beginning of 1988. Prior to the intervent...

Descripción completa

Detalles Bibliográficos
Autores principales: Ross, M, Péraire, S
Lenguaje:eng
Publicado: 1997
Materias:
Acceso en línea:http://cds.cern.ch/record/702411
Descripción
Sumario:A vacuum leak on the internal beam dump TIDV precipitated its replacement in the LSS1 on Monday the 20th of October 1997, the SPS consequently being shut down for three days. The dump had fulfilled its design function since it was installed in the SPS at the beginning of 1988. Prior to the intervention, the Vacuum Group LHC/VAC carried out a number of leak tests, which led to the decision being taken to replace the dump. After the successful intervention, normal machine operation was resumed. Out-gassing of the ten-year-old replacement was initially high, but vacuum pressure is slowly descending to the SPS standard level.