Beam Dump TIDV #1 - Vacuum Failure of 17 Oct. 97

A vacuum leak on the internal beam dump TIDV precipitated its replacement in the LSS1 on Monday the 20th of October 1997, the SPS consequently being shut down for three days. The dump had fulfilled its design function since it was installed in the SPS at the beginning of 1988. Prior to the intervent...