Test Report for Acceptance Test Procedure for Pumping and Instrumentation Control Skid ''K''
This is a Test Report for Acceptance Test Procedure (ATP) HNF-4276. This test report provides the results of the inspection and testing of the new Pumping and Instrumentation Control (PIC) skid designed as ''K''. The ATP was successfully completed. A copy of the completed ATP is...
Autor principal: | Johns, B R |
---|---|
Lenguaje: | eng |
Publicado: |
Fluor Hanford
1999
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/748293 |
Ejemplares similares
-
Acceptance Test Procedure for New Pumping and Instrumentation Control Skid sup L sup
por: Koch, M R
Publicado: (1999) -
105KE Basin Area Radiation Monitor System (ARMS) Acceptance Test Procedure
por: Kinkel, C C
Publicado: (1999) -
Report on the K17 tests
por: CERN. Geneva. Physics III Committee
Publicado: (1972) -
Factory acceptance of the compressor skids at Samifi-Babcock. All pictures show the second stage compressor skid.
por: G. Perinic
Publicado: (2001) -
TPC-sector test procedures
por: Settles, R