Commissioning of the LHC Beam Transfer Line TI 8
The first of the two LHC transfer lines was commissioned in autumn 2004. Beam reached an absorber block located some 2.5 km downstream of the SPS extraction point at the first shot, without the need of any threading. The hardware preparation and commissioning phase will be summarised, followed by a...
Autores principales: | Uythoven, Jan, Arduini, Gianluigi, Chao Yu Chiu, Goddard, Brennan, Jacquet, Delphine, Kain, Verena, Lamont, Mike, Mertens, Volker, Spinks, Alan, Wenninger, Jörg |
---|---|
Lenguaje: | eng |
Publicado: |
2005
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/841097 |
Ejemplares similares
-
Optics Studies of the LHC Beam Transfer Line TI 8
por: Arduini, Gianluigi, et al.
Publicado: (2005) -
Beam Commissioning of the SPS-to-LHC Transfer Line TI 2
por: Uythoven, J, et al.
Publicado: (2008) -
Beam Stability of the LHC Beam Transfer Line TI8
por: Wenninger, Jörg, et al.
Publicado: (2005) -
Beam commissioning of injection into the LHC
por: Mertens, V, et al.
Publicado: (2009) -
Machine studies during beam commissioning of the SPS-to-LHC transfer lines
por: Meddahi, M, et al.