Cargando…

Overhaul of BEBC

The long shutdown of the SPS (from mid of June to the end of 1980) was used for a complete overhaul of the BEBC subsystems, in particular of the refrigerator. Critical features of the chamber (welds, beam windows) were examined by an official inspectorate and pronounced satisfactory. The main modifi...

Descripción completa

Detalles Bibliográficos
Publicado: 1980
Materias:
Acceso en línea:http://cds.cern.ch/record/969762

Ejemplares similares