Construction of an access shaft for LEP

The main contract for underground work in the plain was signed end of February 1983. It foresaw a five-month preparation period before the order to start construction work could be issued. The latter was delivered on 1 September. See Annual Report 1983 p. 114

Detalles Bibliográficos
Publicado: 1983
Materias:
Acceso en línea:http://cds.cern.ch/record/970250
Descripción
Sumario:The main contract for underground work in the plain was signed end of February 1983. It foresaw a five-month preparation period before the order to start construction work could be issued. The latter was delivered on 1 September. See Annual Report 1983 p. 114