Commissioning and Results of the Half-Sector Test Installation with 160 MeV H⁻ beam from Linac4

During the Long Shutdown 2 (LS2) at CERN in 2019/20, the Proton Synchrotron Booster (PSB) will undergo a profound upgrade in the framework of the LHC Injector Upgrade (LIU) project involving also the connection to the new Linac4 injector. The 160 MeV Linac4 H' injection entails a complete repla...

Descripción completa

Detalles Bibliográficos
Autores principales: Mikulec, Bettina, Aguglia, Davide, Allica Santamaria, Juan, Baud, Cedric, Bracco, Chiara, Burger, Stephane, Guidoboni, Greta, Jorat, Louise Olivia, Martin, Christophe, Navarro Fernandez, Araceli, Noulibos, Remy, Roncarolo, Federico, Sanchez Alvarez, Jose-Luis, Tan, Jocelyn, Todorcevic, Todor, Van Trappen, Pieter, Weterings, Wim, Zamantzas, Christos
Lenguaje:eng
Publicado: 2017
Materias:
Acceso en línea:https://dx.doi.org/10.18429/JACoW-IPAC2017-MOPIK047
http://cds.cern.ch/record/2289129