Assembling experience of the first two HIE-ISOLDE cryomodules
The assembly of the first two cryomodules (CM1 and CM2) of the new superconducting linear accelerator HIE-ISOLDE (High Intensity and Energy ISOLDE), located downstream of the REX-ISOLDE normal conducting accelerator, started one year and half ago. After a delicate assembly phase in the cleanroom whi...
Autores principales: | , , , , , , , , , , , , , , , , , , , , , , , |
---|---|
Lenguaje: | eng |
Publicado: |
2017
|
Materias: | |
Acceso en línea: | https://dx.doi.org/10.18429/JACoW-LINAC2016-THPRC016 http://cds.cern.ch/record/2304389 |
_version_ | 1780957463321772032 |
---|---|
author | Therasse, Mathieu Barlow, Graeme Bizzaglia, Sauro Capatina, Ofelia Chrul, Anna Demarest, Paul Dequaire, Julien Deschamps, Jean-Baptiste Gayde, Jean-Christophe Gourragne, Max Harrison, Anthony Kautzmann, Guillaume Leclercq, Yann Mergelkuhl, Dirk Mikkola, Tommi Miyazaki, Akira Parma, Vittorio Somoza, Jose Struik, Michael Teixeira Lopez, Silvia Venturini Delsolaro, Walter Williams, Lloyd Zhang, Pei Garlache, M |
author_facet | Therasse, Mathieu Barlow, Graeme Bizzaglia, Sauro Capatina, Ofelia Chrul, Anna Demarest, Paul Dequaire, Julien Deschamps, Jean-Baptiste Gayde, Jean-Christophe Gourragne, Max Harrison, Anthony Kautzmann, Guillaume Leclercq, Yann Mergelkuhl, Dirk Mikkola, Tommi Miyazaki, Akira Parma, Vittorio Somoza, Jose Struik, Michael Teixeira Lopez, Silvia Venturini Delsolaro, Walter Williams, Lloyd Zhang, Pei Garlache, M |
author_sort | Therasse, Mathieu |
collection | CERN |
description | The assembly of the first two cryomodules (CM1 and CM2) of the new superconducting linear accelerator HIE-ISOLDE (High Intensity and Energy ISOLDE), located downstream of the REX-ISOLDE normal conducting accelerator, started one year and half ago. After a delicate assembly phase in the cleanroom which lasted nine months, the first cryomodule was transported to the ISOLDE hall on 2 May 2015 and coupled to the existing REX-ISOLDE accelerator, increasing the energy of the radioactive ion beams from 2.8 to 4.3 MeV per nucleon. The superconducting linac supplied the CERN-ISOLDE Facility, with radioactive zinc ions until the end of the proton run in November 2015. At the beginning of 2016, the second cryomodule was installed in the machine, increasing the energy to 5.5 MeV per nucleon. During commissioning of the first cryomodule in summer 2015, it was found that the performance of the RF superconductive cavities was limited by the over-heating of their RF couplers. The decision was taken to refurbish CM1 and reinstall it at the end of April. In this paper, we present the challenges faced and the experience gained with the cleanroom assembly of the first two cryomodules, especially the construction of the SC RF cavities and their RF ancillaries. |
id | oai-inspirehep.net-1633274 |
institution | Organización Europea para la Investigación Nuclear |
language | eng |
publishDate | 2017 |
record_format | invenio |
spelling | oai-inspirehep.net-16332742022-03-07T14:38:41Zdoi:10.18429/JACoW-LINAC2016-THPRC016http://cds.cern.ch/record/2304389engTherasse, MathieuBarlow, GraemeBizzaglia, SauroCapatina, OfeliaChrul, AnnaDemarest, PaulDequaire, JulienDeschamps, Jean-BaptisteGayde, Jean-ChristopheGourragne, MaxHarrison, AnthonyKautzmann, GuillaumeLeclercq, YannMergelkuhl, DirkMikkola, TommiMiyazaki, AkiraParma, VittorioSomoza, JoseStruik, MichaelTeixeira Lopez, SilviaVenturini Delsolaro, WalterWilliams, LloydZhang, PeiGarlache, MAssembling experience of the first two HIE-ISOLDE cryomodulesAccelerators and Storage RingsThe assembly of the first two cryomodules (CM1 and CM2) of the new superconducting linear accelerator HIE-ISOLDE (High Intensity and Energy ISOLDE), located downstream of the REX-ISOLDE normal conducting accelerator, started one year and half ago. After a delicate assembly phase in the cleanroom which lasted nine months, the first cryomodule was transported to the ISOLDE hall on 2 May 2015 and coupled to the existing REX-ISOLDE accelerator, increasing the energy of the radioactive ion beams from 2.8 to 4.3 MeV per nucleon. The superconducting linac supplied the CERN-ISOLDE Facility, with radioactive zinc ions until the end of the proton run in November 2015. At the beginning of 2016, the second cryomodule was installed in the machine, increasing the energy to 5.5 MeV per nucleon. During commissioning of the first cryomodule in summer 2015, it was found that the performance of the RF superconductive cavities was limited by the over-heating of their RF couplers. The decision was taken to refurbish CM1 and reinstall it at the end of April. In this paper, we present the challenges faced and the experience gained with the cleanroom assembly of the first two cryomodules, especially the construction of the SC RF cavities and their RF ancillaries.CERN-ACC-2017-347oai:inspirehep.net:16332742017 |
spellingShingle | Accelerators and Storage Rings Therasse, Mathieu Barlow, Graeme Bizzaglia, Sauro Capatina, Ofelia Chrul, Anna Demarest, Paul Dequaire, Julien Deschamps, Jean-Baptiste Gayde, Jean-Christophe Gourragne, Max Harrison, Anthony Kautzmann, Guillaume Leclercq, Yann Mergelkuhl, Dirk Mikkola, Tommi Miyazaki, Akira Parma, Vittorio Somoza, Jose Struik, Michael Teixeira Lopez, Silvia Venturini Delsolaro, Walter Williams, Lloyd Zhang, Pei Garlache, M Assembling experience of the first two HIE-ISOLDE cryomodules |
title | Assembling experience of the first two HIE-ISOLDE cryomodules |
title_full | Assembling experience of the first two HIE-ISOLDE cryomodules |
title_fullStr | Assembling experience of the first two HIE-ISOLDE cryomodules |
title_full_unstemmed | Assembling experience of the first two HIE-ISOLDE cryomodules |
title_short | Assembling experience of the first two HIE-ISOLDE cryomodules |
title_sort | assembling experience of the first two hie-isolde cryomodules |
topic | Accelerators and Storage Rings |
url | https://dx.doi.org/10.18429/JACoW-LINAC2016-THPRC016 http://cds.cern.ch/record/2304389 |
work_keys_str_mv | AT therassemathieu assemblingexperienceofthefirsttwohieisoldecryomodules AT barlowgraeme assemblingexperienceofthefirsttwohieisoldecryomodules AT bizzagliasauro assemblingexperienceofthefirsttwohieisoldecryomodules AT capatinaofelia assemblingexperienceofthefirsttwohieisoldecryomodules AT chrulanna assemblingexperienceofthefirsttwohieisoldecryomodules AT demarestpaul assemblingexperienceofthefirsttwohieisoldecryomodules AT dequairejulien assemblingexperienceofthefirsttwohieisoldecryomodules AT deschampsjeanbaptiste assemblingexperienceofthefirsttwohieisoldecryomodules AT gaydejeanchristophe assemblingexperienceofthefirsttwohieisoldecryomodules AT gourragnemax assemblingexperienceofthefirsttwohieisoldecryomodules AT harrisonanthony assemblingexperienceofthefirsttwohieisoldecryomodules AT kautzmannguillaume assemblingexperienceofthefirsttwohieisoldecryomodules AT leclercqyann assemblingexperienceofthefirsttwohieisoldecryomodules AT mergelkuhldirk assemblingexperienceofthefirsttwohieisoldecryomodules AT mikkolatommi assemblingexperienceofthefirsttwohieisoldecryomodules AT miyazakiakira assemblingexperienceofthefirsttwohieisoldecryomodules AT parmavittorio assemblingexperienceofthefirsttwohieisoldecryomodules AT somozajose assemblingexperienceofthefirsttwohieisoldecryomodules AT struikmichael assemblingexperienceofthefirsttwohieisoldecryomodules AT teixeiralopezsilvia assemblingexperienceofthefirsttwohieisoldecryomodules AT venturinidelsolarowalter assemblingexperienceofthefirsttwohieisoldecryomodules AT williamslloyd assemblingexperienceofthefirsttwohieisoldecryomodules AT zhangpei assemblingexperienceofthefirsttwohieisoldecryomodules AT garlachem assemblingexperienceofthefirsttwohieisoldecryomodules |