LHC YETS recovery
16 days are allocated in March 2016 to prepare the machine for the beam. Around 7000 powering tests will have to be performed to re-commission the superconducting circuits. An extensive list of tests will have to be executed as well on the various systems affected by interventions during YETS. A pre...
Autor principal: | |
---|---|
Lenguaje: | eng |
Publicado: |
CERN
2016
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/2294536 |
Sumario: | 16 days are allocated in March 2016 to prepare the machine for the beam. Around
7000 powering tests will have to be performed to re-commission the
superconducting circuits. An extensive list of tests will have to be executed as
well on the various systems affected by interventions during YETS. A preliminary
planning for these tests will be shown. |
---|