BLMs and thresholds at 6.5/7 TeV
During Long Shutdown 1 the Beam Loss Monitoring system went through several hardware upgrades and general maintenance. Many elements of the system, starting from the tunnel detectors to the threshold-comparator cards were brought from their locations to the lab and refurbished. Almost 30% of the det...
Autores principales: | , , , , , , , , , , , , , , |
---|---|
Lenguaje: | eng |
Publicado: |
CERN
2014
|
Materias: | |
Acceso en línea: | http://cds.cern.ch/record/2295106 |
Sumario: | During Long Shutdown 1 the Beam Loss Monitoring system went through several
hardware upgrades and general maintenance. Many elements of the system, starting
from the tunnel detectors to the threshold-comparator cards were brought from
their locations to the lab and refurbished. Almost 30% of the detectors will be
reinstalled in new positions, optimizing system sensitivity to so called UFO
losses. In order to tune the thresholds on cold magnets a series of quench tests
has been performed during Run 1. An extensive analysis of these tests has been
done leading to suggestions of a new sets of beam abort thresholds. The
threshold setting strategy has been proposed. New tool to generate and set
thresholds is being developed. |
---|