Cargando…
Lessons learned from the HIE-Isolde cavity production and cryomodule commissioning
The HIE-ISOLDE superconducting linac started opera- tions at CERN in 2015 with a first cryomodule hosting five superconducting quarter wave resonators (QWR). These cavities are based on the Nb/Cu technology. In time, two more cryomodules have been assembled, installed and commissioned on line, bring...
Autores principales: | , , , , , , , , , , , , , |
---|---|
Lenguaje: | eng |
Publicado: |
2018
|
Materias: | |
Acceso en línea: | https://dx.doi.org/10.18429/JACoW-SRF2017-TUXAA02 http://cds.cern.ch/record/2673548 |
_version_ | 1780962520802000896 |
---|---|
author | Venturini Delsolaro, Walter Artoos, Kurt Capatina, Ofelia Dr Schirm, Karl-Martin Kadi, Yacine Leclercq, Yann Miyazaki, Akira Montesinos, Eric Parma, Vittorio Rosaz, Guillaume Sublet, Alban Teixeira Lopez, Silvia Therasse, Mathieu Williams, Lloyd |
author_facet | Venturini Delsolaro, Walter Artoos, Kurt Capatina, Ofelia Dr Schirm, Karl-Martin Kadi, Yacine Leclercq, Yann Miyazaki, Akira Montesinos, Eric Parma, Vittorio Rosaz, Guillaume Sublet, Alban Teixeira Lopez, Silvia Therasse, Mathieu Williams, Lloyd |
author_sort | Venturini Delsolaro, Walter |
collection | CERN |
description | The HIE-ISOLDE superconducting linac started opera- tions at CERN in 2015 with a first cryomodule hosting five superconducting quarter wave resonators (QWR). These cavities are based on the Nb/Cu technology. In time, two more cryomodules have been assembled, installed and commissioned on line, bringing the energy reach for the heaviest ions (A/q=4.5) up to 7.5 MeV/u. In 2017, while the first three cryomodules were prepared for the physics run, six more cavities were produced of which five will be installed in a fourth cryomodule. With this, the high beta section of the linac will be complete and the energy will reach 10 MeV/u for A/q=4.5. In this paper we review the experience and lessons learned during the construction of HIE-ISOLDE, along with some still open questions. |
id | oai-inspirehep.net-1669430 |
institution | Organización Europea para la Investigación Nuclear |
language | eng |
publishDate | 2018 |
record_format | invenio |
spelling | oai-inspirehep.net-16694302019-09-30T06:29:59Zdoi:10.18429/JACoW-SRF2017-TUXAA02http://cds.cern.ch/record/2673548engVenturini Delsolaro, WalterArtoos, KurtCapatina, OfeliaDr Schirm, Karl-MartinKadi, YacineLeclercq, YannMiyazaki, AkiraMontesinos, EricParma, VittorioRosaz, GuillaumeSublet, AlbanTeixeira Lopez, SilviaTherasse, MathieuWilliams, LloydLessons learned from the HIE-Isolde cavity production and cryomodule commissioningAccelerators and Storage RingsThe HIE-ISOLDE superconducting linac started opera- tions at CERN in 2015 with a first cryomodule hosting five superconducting quarter wave resonators (QWR). These cavities are based on the Nb/Cu technology. In time, two more cryomodules have been assembled, installed and commissioned on line, bringing the energy reach for the heaviest ions (A/q=4.5) up to 7.5 MeV/u. In 2017, while the first three cryomodules were prepared for the physics run, six more cavities were produced of which five will be installed in a fourth cryomodule. With this, the high beta section of the linac will be complete and the energy will reach 10 MeV/u for A/q=4.5. In this paper we review the experience and lessons learned during the construction of HIE-ISOLDE, along with some still open questions.oai:inspirehep.net:16694302018 |
spellingShingle | Accelerators and Storage Rings Venturini Delsolaro, Walter Artoos, Kurt Capatina, Ofelia Dr Schirm, Karl-Martin Kadi, Yacine Leclercq, Yann Miyazaki, Akira Montesinos, Eric Parma, Vittorio Rosaz, Guillaume Sublet, Alban Teixeira Lopez, Silvia Therasse, Mathieu Williams, Lloyd Lessons learned from the HIE-Isolde cavity production and cryomodule commissioning |
title | Lessons learned from the HIE-Isolde cavity production and cryomodule commissioning |
title_full | Lessons learned from the HIE-Isolde cavity production and cryomodule commissioning |
title_fullStr | Lessons learned from the HIE-Isolde cavity production and cryomodule commissioning |
title_full_unstemmed | Lessons learned from the HIE-Isolde cavity production and cryomodule commissioning |
title_short | Lessons learned from the HIE-Isolde cavity production and cryomodule commissioning |
title_sort | lessons learned from the hie-isolde cavity production and cryomodule commissioning |
topic | Accelerators and Storage Rings |
url | https://dx.doi.org/10.18429/JACoW-SRF2017-TUXAA02 http://cds.cern.ch/record/2673548 |
work_keys_str_mv | AT venturinidelsolarowalter lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT artooskurt lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT capatinaofelia lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT drschirmkarlmartin lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT kadiyacine lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT leclercqyann lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT miyazakiakira lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT montesinoseric lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT parmavittorio lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT rosazguillaume lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT subletalban lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT teixeiralopezsilvia lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT therassemathieu lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning AT williamslloyd lessonslearnedfromthehieisoldecavityproductionandcryomodulecommissioning |