LHC Injectors Upgrade Project: Outlook of the Modifications to the Super Proton Synchrotron (SPS) Vacuum System and Impact on the Operation of the Carbon-Coated Vacuum Chambers

Aiming at doubling the beam intensity and reducing the beam emittance, significant modifications of the LHC and its injector chain will take place during Long Shutdown 2 (LS2), starting from 2019. The LIU project (LHC Injector Upgrade), in the specific, touches Linac4, the Proton Synchrotron Booster...

Descripción completa

Detalles Bibliográficos
Autores principales: Pasquino, Chiara, Bregliozzi, Giuseppe, Chiggiato, Paolo, Cruikshank, Paul, Farricker, Aaron, Harrison, Anthony, Perez Espinos, Jaime, Somoza, Jose, Taborelli, Mauro, Vollinger, Christine, Murteira, D
Lenguaje:eng
Publicado: 2018
Materias:
Acceso en línea:https://dx.doi.org/10.18429/JACoW-IPAC2018-WEPMF087
http://cds.cern.ch/record/2672444
_version_ 1780962529431781376
author Pasquino, Chiara
Bregliozzi, Giuseppe
Chiggiato, Paolo
Cruikshank, Paul
Farricker, Aaron
Harrison, Anthony
Perez Espinos, Jaime
Somoza, Jose
Taborelli, Mauro
Vollinger, Christine
Murteira, D
author_facet Pasquino, Chiara
Bregliozzi, Giuseppe
Chiggiato, Paolo
Cruikshank, Paul
Farricker, Aaron
Harrison, Anthony
Perez Espinos, Jaime
Somoza, Jose
Taborelli, Mauro
Vollinger, Christine
Murteira, D
author_sort Pasquino, Chiara
collection CERN
description Aiming at doubling the beam intensity and reducing the beam emittance, significant modifications of the LHC and its injector chain will take place during Long Shutdown 2 (LS2), starting from 2019. The LIU project (LHC Injector Upgrade), in the specific, touches Linac4, the Proton Synchrotron Booster (PSB), the Proton Synchrotron (PS), the Super Proton Synchrotron (SPS) as well as the heavy ion chain. During LS2, important changes will take place mainly in the Long Straight Sections of the SPS to host a newly conceived dumping system, upgraded RF cavities and upgraded extraction channels. Additionally, the vacuum chambers of the main bending and focusing magnets as well as vacuum drifts will be coated with amorphous carbon in order to reduce the dynamic pressure effects induced by multipacting. The modifications to the different vacuum sectors will be described in details as well as the impact on operation of amorphous carbon coated sectors that have been already deposited.
id oai-inspirehep.net-1690186
institution Organización Europea para la Investigación Nuclear
language eng
publishDate 2018
record_format invenio
spelling oai-inspirehep.net-16901862019-09-30T06:29:59Zdoi:10.18429/JACoW-IPAC2018-WEPMF087http://cds.cern.ch/record/2672444engPasquino, ChiaraBregliozzi, GiuseppeChiggiato, PaoloCruikshank, PaulFarricker, AaronHarrison, AnthonyPerez Espinos, JaimeSomoza, JoseTaborelli, MauroVollinger, ChristineMurteira, DLHC Injectors Upgrade Project: Outlook of the Modifications to the Super Proton Synchrotron (SPS) Vacuum System and Impact on the Operation of the Carbon-Coated Vacuum ChambersAccelerators and Storage RingsAiming at doubling the beam intensity and reducing the beam emittance, significant modifications of the LHC and its injector chain will take place during Long Shutdown 2 (LS2), starting from 2019. The LIU project (LHC Injector Upgrade), in the specific, touches Linac4, the Proton Synchrotron Booster (PSB), the Proton Synchrotron (PS), the Super Proton Synchrotron (SPS) as well as the heavy ion chain. During LS2, important changes will take place mainly in the Long Straight Sections of the SPS to host a newly conceived dumping system, upgraded RF cavities and upgraded extraction channels. Additionally, the vacuum chambers of the main bending and focusing magnets as well as vacuum drifts will be coated with amorphous carbon in order to reduce the dynamic pressure effects induced by multipacting. The modifications to the different vacuum sectors will be described in details as well as the impact on operation of amorphous carbon coated sectors that have been already deposited.Aiming at doubling the beam intensity and reducing the beam emittance [1], significant modifications of the LHC injector chain will take place during Long Shutdown 2 (LS2), starting from 2019. The LIU project (LHC Injector Upgrade) [2], in the specific, touches Linac4, the Proton Synchrotron Booster (PSB), the Proton Synchrotron (PS), the Super Proton Synchrotron (SPS). During LS2, im- portant changes will take place mainly in the Long Straight Sections of the SPS to host a newly conceived dumping system, upgrade RF cavities and the extraction transfer lines. Additionally, the vacuum chambers of some main bending and focusing magnets, as well as vacuum drifts, will be coated with amorphous carbon coating (aC) in or- der to minimise the induced beam instabilities due to elec- tron multipacting[3]. The guidelines followed to conceive and design the new vacuum sectors will be described here- after and a first glance at the impact on the operation of aC coated chambers will be given.oai:inspirehep.net:16901862018
spellingShingle Accelerators and Storage Rings
Pasquino, Chiara
Bregliozzi, Giuseppe
Chiggiato, Paolo
Cruikshank, Paul
Farricker, Aaron
Harrison, Anthony
Perez Espinos, Jaime
Somoza, Jose
Taborelli, Mauro
Vollinger, Christine
Murteira, D
LHC Injectors Upgrade Project: Outlook of the Modifications to the Super Proton Synchrotron (SPS) Vacuum System and Impact on the Operation of the Carbon-Coated Vacuum Chambers
title LHC Injectors Upgrade Project: Outlook of the Modifications to the Super Proton Synchrotron (SPS) Vacuum System and Impact on the Operation of the Carbon-Coated Vacuum Chambers
title_full LHC Injectors Upgrade Project: Outlook of the Modifications to the Super Proton Synchrotron (SPS) Vacuum System and Impact on the Operation of the Carbon-Coated Vacuum Chambers
title_fullStr LHC Injectors Upgrade Project: Outlook of the Modifications to the Super Proton Synchrotron (SPS) Vacuum System and Impact on the Operation of the Carbon-Coated Vacuum Chambers
title_full_unstemmed LHC Injectors Upgrade Project: Outlook of the Modifications to the Super Proton Synchrotron (SPS) Vacuum System and Impact on the Operation of the Carbon-Coated Vacuum Chambers
title_short LHC Injectors Upgrade Project: Outlook of the Modifications to the Super Proton Synchrotron (SPS) Vacuum System and Impact on the Operation of the Carbon-Coated Vacuum Chambers
title_sort lhc injectors upgrade project: outlook of the modifications to the super proton synchrotron (sps) vacuum system and impact on the operation of the carbon-coated vacuum chambers
topic Accelerators and Storage Rings
url https://dx.doi.org/10.18429/JACoW-IPAC2018-WEPMF087
http://cds.cern.ch/record/2672444
work_keys_str_mv AT pasquinochiara lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT bregliozzigiuseppe lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT chiggiatopaolo lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT cruikshankpaul lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT farrickeraaron lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT harrisonanthony lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT perezespinosjaime lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT somozajose lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT taborellimauro lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT vollingerchristine lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers
AT murteirad lhcinjectorsupgradeprojectoutlookofthemodificationstothesuperprotonsynchrotronspsvacuumsystemandimpactontheoperationofthecarboncoatedvacuumchambers