Validation of the CERN PS Eddy Current Injection Septa

As part of the upgrade of the CERN PS accelerator from 1.4 GeV to 2 GeV, new injection septa have been developed. The system is comprised of a pulsed eddy current septum magnet and a pulsed eddy current bumper magnet. Both magnets will be housed in a common vacuum vessel and powered by independent p...

Descripción completa

Detalles Bibliográficos
Autores principales: Hourican, Michael, Balhan, Bruno, Borburgh, Jan, Masson, Thierry, Sanz Ull, Alejandro
Lenguaje:eng
Publicado: 2018
Materias:
Acceso en línea:https://dx.doi.org/10.18429/JACoW-IPAC2018-TUPAF037
http://cds.cern.ch/record/2666853
Descripción
Sumario:As part of the upgrade of the CERN PS accelerator from 1.4 GeV to 2 GeV, new injection septa have been developed. The system is comprised of a pulsed eddy current septum magnet and a pulsed eddy current bumper magnet. Both magnets will be housed in a common vacuum vessel and powered by independent power converters. In-depth studies and simulations have been performed to reduce as much as possible the leak field by designing specific magnetic shielding, combined with dual function beam impedance shielding. A prototype magnet was built and measured to validate the simulations. The final complete system will be bake-able at 200C and uses demineralised water for cooling. Closed circuit cooling systems have been integrated to reduce risks of vacuum leaks. This report describes the electromechanical design from the concept and simulation stages to the prototyping and final manufacturing. Results of the initial magnetic measurements, including field homogeneity and leak field mitigation methods are presented.