Design, Procurement, Installation and Commissioning of the Cryogenic Infrastructure for a New Superconducting RF Test Facility with Beam at CERN
The High-Luminosity LHC project (HL–LHC), aiming at peak luminosity above 5.0 × 10$^{34}$ cm$^{-2}$ s$^{-1}$, considers replacing the matching sections on both sides of the ATLAS and CMS experiments. To complement new focusing quadrupoles, this upgrade considers using the so-called superconducting c...
Autores principales: | Delprat, L, Brodzinski, K, Claudet, S, Derking, H |
---|---|
Lenguaje: | eng |
Publicado: |
IOP
2020
|
Materias: | |
Acceso en línea: | https://dx.doi.org/10.1088/1757-899X/755/1/012145 http://cds.cern.ch/record/2725617 |
Ejemplares similares
-
Cryogenic design of the crab cavity modules for the High Luminosity LHC at CERN
por: Brodzinski, K, et al.
Publicado: (2022) -
Commissioning and performance of the cryogenic system of the new test facility for large superconducting devices at CERN
por: Derking, J H, et al.
Publicado: (2019) -
Design, Construction, Installation and First Commissioning Results of the LHC Cryogenic System
por: Claudet, S
Publicado: (2006) -
Upgrade of the cryogenic infrastructure of SM18, CERN main test facility for superconducting magnets and RF cavities
por: Perin, A, et al.
Publicado: (2017) -
LHC cryogenics – new experience of run with increased beam energy and intensity
por: Brodzinski, K, et al.