Cargando…
Run 2 Overview of the LHC Beam Instrumentation
This papers reviews the implemented improvements, operational experience, and performance reach of the major LHC Beam Instrumentation systems, excluding transverse beam profile diagnostics, throughout the LHC Run 2. The major hardware and software changes since the Long Shutdown 1 (LS1) are highligh...
Autores principales: | , , , , , , , |
---|---|
Lenguaje: | eng |
Publicado: |
2019
|
Acceso en línea: | http://cds.cern.ch/record/2750284 |
Sumario: | This papers reviews the implemented improvements, operational experience, and
performance reach of the major LHC Beam Instrumentation systems, excluding
transverse beam profile diagnostics, throughout the LHC Run 2. The major
hardware and software changes since the Long Shutdown 1 (LS1) are highlighted
and the main actions addressing the remaining open issues during the Long
Shutdown 2 (LS2) are listed. An outlook for the post-LS2 commissioning is
provided based on the experience gained during the Run 2 commissioning period. |
---|