Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project

This paper presents an extension of the multimode resource-constrained project scheduling problem for a large scale construction project where multiple parallel projects and a fuzzy random environment are considered. By taking into account the most typical goals in project management, a cost/weighte...

Descripción completa

Detalles Bibliográficos
Autores principales: Xu, Jiuping, Feng, Cuiying
Formato: Online Artículo Texto
Lenguaje:English
Publicado: Hindawi Publishing Corporation 2014
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3914335/
https://www.ncbi.nlm.nih.gov/pubmed/24550708
http://dx.doi.org/10.1155/2014/463692
_version_ 1782302387111723008
author Xu, Jiuping
Feng, Cuiying
author_facet Xu, Jiuping
Feng, Cuiying
author_sort Xu, Jiuping
collection PubMed
description This paper presents an extension of the multimode resource-constrained project scheduling problem for a large scale construction project where multiple parallel projects and a fuzzy random environment are considered. By taking into account the most typical goals in project management, a cost/weighted makespan/quality trade-off optimization model is constructed. To deal with the uncertainties, a hybrid crisp approach is used to transform the fuzzy random parameters into fuzzy variables that are subsequently defuzzified using an expected value operator with an optimistic-pessimistic index. Then a combinatorial-priority-based hybrid particle swarm optimization algorithm is developed to solve the proposed model, where the combinatorial particle swarm optimization and priority-based particle swarm optimization are designed to assign modes to activities and to schedule activities, respectively. Finally, the results and analysis of a practical example at a large scale hydropower construction project are presented to demonstrate the practicality and efficiency of the proposed model and optimization method.
format Online
Article
Text
id pubmed-3914335
institution National Center for Biotechnology Information
language English
publishDate 2014
publisher Hindawi Publishing Corporation
record_format MEDLINE/PubMed
spelling pubmed-39143352014-02-18 Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project Xu, Jiuping Feng, Cuiying ScientificWorldJournal Research Article This paper presents an extension of the multimode resource-constrained project scheduling problem for a large scale construction project where multiple parallel projects and a fuzzy random environment are considered. By taking into account the most typical goals in project management, a cost/weighted makespan/quality trade-off optimization model is constructed. To deal with the uncertainties, a hybrid crisp approach is used to transform the fuzzy random parameters into fuzzy variables that are subsequently defuzzified using an expected value operator with an optimistic-pessimistic index. Then a combinatorial-priority-based hybrid particle swarm optimization algorithm is developed to solve the proposed model, where the combinatorial particle swarm optimization and priority-based particle swarm optimization are designed to assign modes to activities and to schedule activities, respectively. Finally, the results and analysis of a practical example at a large scale hydropower construction project are presented to demonstrate the practicality and efficiency of the proposed model and optimization method. Hindawi Publishing Corporation 2014-01-15 /pmc/articles/PMC3914335/ /pubmed/24550708 http://dx.doi.org/10.1155/2014/463692 Text en Copyright © 2014 J. Xu and C. Feng. https://creativecommons.org/licenses/by/3.0/ This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
spellingShingle Research Article
Xu, Jiuping
Feng, Cuiying
Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project
title Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project
title_full Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project
title_fullStr Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project
title_full_unstemmed Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project
title_short Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project
title_sort multimode resource-constrained multiple project scheduling problem under fuzzy random environment and its application to a large scale hydropower construction project
topic Research Article
url https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3914335/
https://www.ncbi.nlm.nih.gov/pubmed/24550708
http://dx.doi.org/10.1155/2014/463692
work_keys_str_mv AT xujiuping multimoderesourceconstrainedmultipleprojectschedulingproblemunderfuzzyrandomenvironmentanditsapplicationtoalargescalehydropowerconstructionproject
AT fengcuiying multimoderesourceconstrainedmultipleprojectschedulingproblemunderfuzzyrandomenvironmentanditsapplicationtoalargescalehydropowerconstructionproject