Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project
This paper presents an extension of the multimode resource-constrained project scheduling problem for a large scale construction project where multiple parallel projects and a fuzzy random environment are considered. By taking into account the most typical goals in project management, a cost/weighte...
Autores principales: | , |
---|---|
Formato: | Online Artículo Texto |
Lenguaje: | English |
Publicado: |
Hindawi Publishing Corporation
2014
|
Materias: | |
Acceso en línea: | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3914335/ https://www.ncbi.nlm.nih.gov/pubmed/24550708 http://dx.doi.org/10.1155/2014/463692 |
_version_ | 1782302387111723008 |
---|---|
author | Xu, Jiuping Feng, Cuiying |
author_facet | Xu, Jiuping Feng, Cuiying |
author_sort | Xu, Jiuping |
collection | PubMed |
description | This paper presents an extension of the multimode resource-constrained project scheduling problem for a large scale construction project where multiple parallel projects and a fuzzy random environment are considered. By taking into account the most typical goals in project management, a cost/weighted makespan/quality trade-off optimization model is constructed. To deal with the uncertainties, a hybrid crisp approach is used to transform the fuzzy random parameters into fuzzy variables that are subsequently defuzzified using an expected value operator with an optimistic-pessimistic index. Then a combinatorial-priority-based hybrid particle swarm optimization algorithm is developed to solve the proposed model, where the combinatorial particle swarm optimization and priority-based particle swarm optimization are designed to assign modes to activities and to schedule activities, respectively. Finally, the results and analysis of a practical example at a large scale hydropower construction project are presented to demonstrate the practicality and efficiency of the proposed model and optimization method. |
format | Online Article Text |
id | pubmed-3914335 |
institution | National Center for Biotechnology Information |
language | English |
publishDate | 2014 |
publisher | Hindawi Publishing Corporation |
record_format | MEDLINE/PubMed |
spelling | pubmed-39143352014-02-18 Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project Xu, Jiuping Feng, Cuiying ScientificWorldJournal Research Article This paper presents an extension of the multimode resource-constrained project scheduling problem for a large scale construction project where multiple parallel projects and a fuzzy random environment are considered. By taking into account the most typical goals in project management, a cost/weighted makespan/quality trade-off optimization model is constructed. To deal with the uncertainties, a hybrid crisp approach is used to transform the fuzzy random parameters into fuzzy variables that are subsequently defuzzified using an expected value operator with an optimistic-pessimistic index. Then a combinatorial-priority-based hybrid particle swarm optimization algorithm is developed to solve the proposed model, where the combinatorial particle swarm optimization and priority-based particle swarm optimization are designed to assign modes to activities and to schedule activities, respectively. Finally, the results and analysis of a practical example at a large scale hydropower construction project are presented to demonstrate the practicality and efficiency of the proposed model and optimization method. Hindawi Publishing Corporation 2014-01-15 /pmc/articles/PMC3914335/ /pubmed/24550708 http://dx.doi.org/10.1155/2014/463692 Text en Copyright © 2014 J. Xu and C. Feng. https://creativecommons.org/licenses/by/3.0/ This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. |
spellingShingle | Research Article Xu, Jiuping Feng, Cuiying Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project |
title | Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a
Large Scale Hydropower Construction Project |
title_full | Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a
Large Scale Hydropower Construction Project |
title_fullStr | Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a
Large Scale Hydropower Construction Project |
title_full_unstemmed | Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a
Large Scale Hydropower Construction Project |
title_short | Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a
Large Scale Hydropower Construction Project |
title_sort | multimode resource-constrained multiple project scheduling problem under fuzzy random environment and its application to a
large scale hydropower construction project |
topic | Research Article |
url | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3914335/ https://www.ncbi.nlm.nih.gov/pubmed/24550708 http://dx.doi.org/10.1155/2014/463692 |
work_keys_str_mv | AT xujiuping multimoderesourceconstrainedmultipleprojectschedulingproblemunderfuzzyrandomenvironmentanditsapplicationtoalargescalehydropowerconstructionproject AT fengcuiying multimoderesourceconstrainedmultipleprojectschedulingproblemunderfuzzyrandomenvironmentanditsapplicationtoalargescalehydropowerconstructionproject |