An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation
The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to opti...
Autores principales: | , |
---|---|
Formato: | Online Artículo Texto |
Lenguaje: | English |
Publicado: |
Hindawi Publishing Corporation
2014
|
Materias: | |
Acceso en línea: | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3929567/ https://www.ncbi.nlm.nih.gov/pubmed/24672351 http://dx.doi.org/10.1155/2014/673248 |
_version_ | 1782304409583091712 |
---|---|
author | Hu, Wenfa He, Xinhua |
author_facet | Hu, Wenfa He, Xinhua |
author_sort | Hu, Wenfa |
collection | PubMed |
description | The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to optimize multiobjectives. The model is from the project breakdown structure method where task resources in a construction project are divided into a series of activities and further into construction labors, materials, equipment, and administration. The resources utilized in a construction activity would eventually determine its construction time, cost, and quality, and a complex time-cost-quality trade-off model is finally generated based on correlations between construction activities. A genetic algorithm tool is applied in the model to solve the comprehensive nonlinear time-cost-quality problems. Building of a three-storey house is an example to illustrate the implementation of the model, demonstrate its advantages in optimizing trade-off of construction time, cost, and quality, and help make a winning decision in construction practices. The computational time-cost-quality curves in visual graphics from the case study prove traditional cost-time assumptions reasonable and also prove this time-cost-quality trade-off model sophisticated. |
format | Online Article Text |
id | pubmed-3929567 |
institution | National Center for Biotechnology Information |
language | English |
publishDate | 2014 |
publisher | Hindawi Publishing Corporation |
record_format | MEDLINE/PubMed |
spelling | pubmed-39295672014-03-26 An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation Hu, Wenfa He, Xinhua ScientificWorldJournal Research Article The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to optimize multiobjectives. The model is from the project breakdown structure method where task resources in a construction project are divided into a series of activities and further into construction labors, materials, equipment, and administration. The resources utilized in a construction activity would eventually determine its construction time, cost, and quality, and a complex time-cost-quality trade-off model is finally generated based on correlations between construction activities. A genetic algorithm tool is applied in the model to solve the comprehensive nonlinear time-cost-quality problems. Building of a three-storey house is an example to illustrate the implementation of the model, demonstrate its advantages in optimizing trade-off of construction time, cost, and quality, and help make a winning decision in construction practices. The computational time-cost-quality curves in visual graphics from the case study prove traditional cost-time assumptions reasonable and also prove this time-cost-quality trade-off model sophisticated. Hindawi Publishing Corporation 2014-01-30 /pmc/articles/PMC3929567/ /pubmed/24672351 http://dx.doi.org/10.1155/2014/673248 Text en Copyright © 2014 W. Hu and X. He. https://creativecommons.org/licenses/by/3.0/ This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. |
spellingShingle | Research Article Hu, Wenfa He, Xinhua An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation |
title | An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation |
title_full | An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation |
title_fullStr | An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation |
title_full_unstemmed | An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation |
title_short | An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation |
title_sort | innovative time-cost-quality tradeoff modeling of building construction project based on resource allocation |
topic | Research Article |
url | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3929567/ https://www.ncbi.nlm.nih.gov/pubmed/24672351 http://dx.doi.org/10.1155/2014/673248 |
work_keys_str_mv | AT huwenfa aninnovativetimecostqualitytradeoffmodelingofbuildingconstructionprojectbasedonresourceallocation AT hexinhua aninnovativetimecostqualitytradeoffmodelingofbuildingconstructionprojectbasedonresourceallocation AT huwenfa innovativetimecostqualitytradeoffmodelingofbuildingconstructionprojectbasedonresourceallocation AT hexinhua innovativetimecostqualitytradeoffmodelingofbuildingconstructionprojectbasedonresourceallocation |