An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation

The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to opti...

Descripción completa

Detalles Bibliográficos
Autores principales: Hu, Wenfa, He, Xinhua
Formato: Online Artículo Texto
Lenguaje:English
Publicado: Hindawi Publishing Corporation 2014
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3929567/
https://www.ncbi.nlm.nih.gov/pubmed/24672351
http://dx.doi.org/10.1155/2014/673248
_version_ 1782304409583091712
author Hu, Wenfa
He, Xinhua
author_facet Hu, Wenfa
He, Xinhua
author_sort Hu, Wenfa
collection PubMed
description The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to optimize multiobjectives. The model is from the project breakdown structure method where task resources in a construction project are divided into a series of activities and further into construction labors, materials, equipment, and administration. The resources utilized in a construction activity would eventually determine its construction time, cost, and quality, and a complex time-cost-quality trade-off model is finally generated based on correlations between construction activities. A genetic algorithm tool is applied in the model to solve the comprehensive nonlinear time-cost-quality problems. Building of a three-storey house is an example to illustrate the implementation of the model, demonstrate its advantages in optimizing trade-off of construction time, cost, and quality, and help make a winning decision in construction practices. The computational time-cost-quality curves in visual graphics from the case study prove traditional cost-time assumptions reasonable and also prove this time-cost-quality trade-off model sophisticated.
format Online
Article
Text
id pubmed-3929567
institution National Center for Biotechnology Information
language English
publishDate 2014
publisher Hindawi Publishing Corporation
record_format MEDLINE/PubMed
spelling pubmed-39295672014-03-26 An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation Hu, Wenfa He, Xinhua ScientificWorldJournal Research Article The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to optimize multiobjectives. The model is from the project breakdown structure method where task resources in a construction project are divided into a series of activities and further into construction labors, materials, equipment, and administration. The resources utilized in a construction activity would eventually determine its construction time, cost, and quality, and a complex time-cost-quality trade-off model is finally generated based on correlations between construction activities. A genetic algorithm tool is applied in the model to solve the comprehensive nonlinear time-cost-quality problems. Building of a three-storey house is an example to illustrate the implementation of the model, demonstrate its advantages in optimizing trade-off of construction time, cost, and quality, and help make a winning decision in construction practices. The computational time-cost-quality curves in visual graphics from the case study prove traditional cost-time assumptions reasonable and also prove this time-cost-quality trade-off model sophisticated. Hindawi Publishing Corporation 2014-01-30 /pmc/articles/PMC3929567/ /pubmed/24672351 http://dx.doi.org/10.1155/2014/673248 Text en Copyright © 2014 W. Hu and X. He. https://creativecommons.org/licenses/by/3.0/ This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
spellingShingle Research Article
Hu, Wenfa
He, Xinhua
An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation
title An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation
title_full An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation
title_fullStr An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation
title_full_unstemmed An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation
title_short An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation
title_sort innovative time-cost-quality tradeoff modeling of building construction project based on resource allocation
topic Research Article
url https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3929567/
https://www.ncbi.nlm.nih.gov/pubmed/24672351
http://dx.doi.org/10.1155/2014/673248
work_keys_str_mv AT huwenfa aninnovativetimecostqualitytradeoffmodelingofbuildingconstructionprojectbasedonresourceallocation
AT hexinhua aninnovativetimecostqualitytradeoffmodelingofbuildingconstructionprojectbasedonresourceallocation
AT huwenfa innovativetimecostqualitytradeoffmodelingofbuildingconstructionprojectbasedonresourceallocation
AT hexinhua innovativetimecostqualitytradeoffmodelingofbuildingconstructionprojectbasedonresourceallocation