Scheduling Projects with Multiskill Learning Effect
We investigate the project scheduling problem with multiskill learning effect. A new model is proposed to deal with the problem, where both autonomous and induced learning are considered. In order to obtain the optimal solution, a genetic algorithm with specific encoding and decoding schemes is intr...
Autores principales: | , |
---|---|
Formato: | Online Artículo Texto |
Lenguaje: | English |
Publicado: |
Hindawi Publishing Corporation
2014
|
Materias: | |
Acceso en línea: | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3934581/ https://www.ncbi.nlm.nih.gov/pubmed/24683355 http://dx.doi.org/10.1155/2014/731081 |
_version_ | 1782305072923803648 |
---|---|
author | Zha, Hong Zhang, Lianying |
author_facet | Zha, Hong Zhang, Lianying |
author_sort | Zha, Hong |
collection | PubMed |
description | We investigate the project scheduling problem with multiskill learning effect. A new model is proposed to deal with the problem, where both autonomous and induced learning are considered. In order to obtain the optimal solution, a genetic algorithm with specific encoding and decoding schemes is introduced. A numerical example is used to illustrate the proposed model. The computational results show that the learning effect cannot be neglected in project scheduling. By means of determining the level of induced learning, the project manager can balance the project makespan with total cost. |
format | Online Article Text |
id | pubmed-3934581 |
institution | National Center for Biotechnology Information |
language | English |
publishDate | 2014 |
publisher | Hindawi Publishing Corporation |
record_format | MEDLINE/PubMed |
spelling | pubmed-39345812014-03-30 Scheduling Projects with Multiskill Learning Effect Zha, Hong Zhang, Lianying ScientificWorldJournal Research Article We investigate the project scheduling problem with multiskill learning effect. A new model is proposed to deal with the problem, where both autonomous and induced learning are considered. In order to obtain the optimal solution, a genetic algorithm with specific encoding and decoding schemes is introduced. A numerical example is used to illustrate the proposed model. The computational results show that the learning effect cannot be neglected in project scheduling. By means of determining the level of induced learning, the project manager can balance the project makespan with total cost. Hindawi Publishing Corporation 2014-02-10 /pmc/articles/PMC3934581/ /pubmed/24683355 http://dx.doi.org/10.1155/2014/731081 Text en Copyright © 2014 H. Zha and L. Zhang. https://creativecommons.org/licenses/by/3.0/ This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. |
spellingShingle | Research Article Zha, Hong Zhang, Lianying Scheduling Projects with Multiskill Learning Effect |
title | Scheduling Projects with Multiskill Learning Effect |
title_full | Scheduling Projects with Multiskill Learning Effect |
title_fullStr | Scheduling Projects with Multiskill Learning Effect |
title_full_unstemmed | Scheduling Projects with Multiskill Learning Effect |
title_short | Scheduling Projects with Multiskill Learning Effect |
title_sort | scheduling projects with multiskill learning effect |
topic | Research Article |
url | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC3934581/ https://www.ncbi.nlm.nih.gov/pubmed/24683355 http://dx.doi.org/10.1155/2014/731081 |
work_keys_str_mv | AT zhahong schedulingprojectswithmultiskilllearningeffect AT zhanglianying schedulingprojectswithmultiskilllearningeffect |