Integrated Production and Distribution Scheduling Problems Related to Fixed Delivery Departure Dates and Weights of Late Orders

We consider an integrated production and distribution scheduling problem faced by a typical make-to-order manufacturer which relies on a third-party logistics (3PL) provider for finished product delivery to customers. In the beginning of a planning horizon, the manufacturer has received a set of ord...

Descripción completa

Detalles Bibliográficos
Autores principales: Li, Shanlin, Li, Maoqin
Formato: Online Artículo Texto
Lenguaje:English
Publicado: Hindawi Publishing Corporation 2015
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC4345271/
https://www.ncbi.nlm.nih.gov/pubmed/25785285
http://dx.doi.org/10.1155/2015/804968
_version_ 1782359557755895808
author Li, Shanlin
Li, Maoqin
author_facet Li, Shanlin
Li, Maoqin
author_sort Li, Shanlin
collection PubMed
description We consider an integrated production and distribution scheduling problem faced by a typical make-to-order manufacturer which relies on a third-party logistics (3PL) provider for finished product delivery to customers. In the beginning of a planning horizon, the manufacturer has received a set of orders to be processed on a single production line. Completed orders are delivered to customers by a finite number of vehicles provided by the 3PL company which follows a fixed daily or weekly shipping schedule such that the vehicles have fixed departure dates which are not part of the decisions. The problem is to find a feasible schedule that minimizes one of the following objective functions when processing times and weights are oppositely ordered: (1) the total weight of late orders and (2) the number of vehicles used subject to the condition that the total weight of late orders is minimum. We show that both problems are solvable in polynomial time.
format Online
Article
Text
id pubmed-4345271
institution National Center for Biotechnology Information
language English
publishDate 2015
publisher Hindawi Publishing Corporation
record_format MEDLINE/PubMed
spelling pubmed-43452712015-03-17 Integrated Production and Distribution Scheduling Problems Related to Fixed Delivery Departure Dates and Weights of Late Orders Li, Shanlin Li, Maoqin ScientificWorldJournal Research Article We consider an integrated production and distribution scheduling problem faced by a typical make-to-order manufacturer which relies on a third-party logistics (3PL) provider for finished product delivery to customers. In the beginning of a planning horizon, the manufacturer has received a set of orders to be processed on a single production line. Completed orders are delivered to customers by a finite number of vehicles provided by the 3PL company which follows a fixed daily or weekly shipping schedule such that the vehicles have fixed departure dates which are not part of the decisions. The problem is to find a feasible schedule that minimizes one of the following objective functions when processing times and weights are oppositely ordered: (1) the total weight of late orders and (2) the number of vehicles used subject to the condition that the total weight of late orders is minimum. We show that both problems are solvable in polynomial time. Hindawi Publishing Corporation 2015 2015-02-16 /pmc/articles/PMC4345271/ /pubmed/25785285 http://dx.doi.org/10.1155/2015/804968 Text en Copyright © 2015 S. Li and M. Li. https://creativecommons.org/licenses/by/3.0/ This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
spellingShingle Research Article
Li, Shanlin
Li, Maoqin
Integrated Production and Distribution Scheduling Problems Related to Fixed Delivery Departure Dates and Weights of Late Orders
title Integrated Production and Distribution Scheduling Problems Related to Fixed Delivery Departure Dates and Weights of Late Orders
title_full Integrated Production and Distribution Scheduling Problems Related to Fixed Delivery Departure Dates and Weights of Late Orders
title_fullStr Integrated Production and Distribution Scheduling Problems Related to Fixed Delivery Departure Dates and Weights of Late Orders
title_full_unstemmed Integrated Production and Distribution Scheduling Problems Related to Fixed Delivery Departure Dates and Weights of Late Orders
title_short Integrated Production and Distribution Scheduling Problems Related to Fixed Delivery Departure Dates and Weights of Late Orders
title_sort integrated production and distribution scheduling problems related to fixed delivery departure dates and weights of late orders
topic Research Article
url https://www.ncbi.nlm.nih.gov/pmc/articles/PMC4345271/
https://www.ncbi.nlm.nih.gov/pubmed/25785285
http://dx.doi.org/10.1155/2015/804968
work_keys_str_mv AT lishanlin integratedproductionanddistributionschedulingproblemsrelatedtofixeddeliverydeparturedatesandweightsoflateorders
AT limaoqin integratedproductionanddistributionschedulingproblemsrelatedtofixeddeliverydeparturedatesandweightsoflateorders