Forecasting and prevention of water inrush during the excavation process of a diversion tunnel at the Jinping II Hydropower Station, China
INTRODUCTION: Estimating groundwater inflow into a tunnel before and during the excavation process is an important task to ensure the safety and schedule during the underground construction process. CASE DESCRIPTION: Here we report a case of the forecasting and prevention of water inrush at the Jinp...
Autores principales: | , , , , |
---|---|
Formato: | Online Artículo Texto |
Lenguaje: | English |
Publicado: |
Springer International Publishing
2016
|
Materias: | |
Acceso en línea: | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC4899345/ https://www.ncbi.nlm.nih.gov/pubmed/27347472 http://dx.doi.org/10.1186/s40064-016-2336-9 |
_version_ | 1782436445542154240 |
---|---|
author | Hou, Tian-xing Yang, Xing-guo Xing, Hui-ge Huang, Kang-xin Zhou, Jia-wen |
author_facet | Hou, Tian-xing Yang, Xing-guo Xing, Hui-ge Huang, Kang-xin Zhou, Jia-wen |
author_sort | Hou, Tian-xing |
collection | PubMed |
description | INTRODUCTION: Estimating groundwater inflow into a tunnel before and during the excavation process is an important task to ensure the safety and schedule during the underground construction process. CASE DESCRIPTION: Here we report a case of the forecasting and prevention of water inrush at the Jinping II Hydropower Station diversion tunnel groups during the excavation process. The diversion tunnel groups are located in mountains and valleys, and with high water pressure head. Three forecasting methods are used to predict the total water inflow of the #2 diversion tunnel. Furthermore, based on the accurate estimation of the water inrush around the tunnel working area, a theoretical method is presented to forecast the water inflow at the working area during the excavation process. DISCUSSION AND EVALUATION: The simulated results show that the total water flow is 1586.9, 1309.4 and 2070.2 m(3)/h using the Qshima method, Kostyakov method and Ochiai method, respectively. The Qshima method is the best one because it most closely matches the monitoring result. According to the huge water inflow into the #2 diversion tunnel, reasonable drainage measures are arranged to prevent the potential disaster of water inrush. The groundwater pressure head can be determined using the water flow velocity from the advancing holes; then, the groundwater pressure head can be used to predict the possible water inflow. The simulated results show that the groundwater pressure head and water inflow re stable and relatively small around the region of the intact rock mass, but there is a sudden change around the fault region with a large water inflow and groundwater pressure head. Different countermeasures are adopted to prevent water inrush disasters during the tunnel excavation process. CONCLUSION: Reasonable forecasting the characteristic parameters of water inrush is very useful for the formation of prevention and mitigation schemes during the tunnel excavation process. |
format | Online Article Text |
id | pubmed-4899345 |
institution | National Center for Biotechnology Information |
language | English |
publishDate | 2016 |
publisher | Springer International Publishing |
record_format | MEDLINE/PubMed |
spelling | pubmed-48993452016-06-24 Forecasting and prevention of water inrush during the excavation process of a diversion tunnel at the Jinping II Hydropower Station, China Hou, Tian-xing Yang, Xing-guo Xing, Hui-ge Huang, Kang-xin Zhou, Jia-wen Springerplus Case Study INTRODUCTION: Estimating groundwater inflow into a tunnel before and during the excavation process is an important task to ensure the safety and schedule during the underground construction process. CASE DESCRIPTION: Here we report a case of the forecasting and prevention of water inrush at the Jinping II Hydropower Station diversion tunnel groups during the excavation process. The diversion tunnel groups are located in mountains and valleys, and with high water pressure head. Three forecasting methods are used to predict the total water inflow of the #2 diversion tunnel. Furthermore, based on the accurate estimation of the water inrush around the tunnel working area, a theoretical method is presented to forecast the water inflow at the working area during the excavation process. DISCUSSION AND EVALUATION: The simulated results show that the total water flow is 1586.9, 1309.4 and 2070.2 m(3)/h using the Qshima method, Kostyakov method and Ochiai method, respectively. The Qshima method is the best one because it most closely matches the monitoring result. According to the huge water inflow into the #2 diversion tunnel, reasonable drainage measures are arranged to prevent the potential disaster of water inrush. The groundwater pressure head can be determined using the water flow velocity from the advancing holes; then, the groundwater pressure head can be used to predict the possible water inflow. The simulated results show that the groundwater pressure head and water inflow re stable and relatively small around the region of the intact rock mass, but there is a sudden change around the fault region with a large water inflow and groundwater pressure head. Different countermeasures are adopted to prevent water inrush disasters during the tunnel excavation process. CONCLUSION: Reasonable forecasting the characteristic parameters of water inrush is very useful for the formation of prevention and mitigation schemes during the tunnel excavation process. Springer International Publishing 2016-05-23 /pmc/articles/PMC4899345/ /pubmed/27347472 http://dx.doi.org/10.1186/s40064-016-2336-9 Text en © The Author(s). 2016 Open AccessThis article is distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution, and reproduction in any medium, provided you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons license, and indicate if changes were made. |
spellingShingle | Case Study Hou, Tian-xing Yang, Xing-guo Xing, Hui-ge Huang, Kang-xin Zhou, Jia-wen Forecasting and prevention of water inrush during the excavation process of a diversion tunnel at the Jinping II Hydropower Station, China |
title | Forecasting and prevention of water inrush during the excavation process of a diversion tunnel at the Jinping II Hydropower Station, China |
title_full | Forecasting and prevention of water inrush during the excavation process of a diversion tunnel at the Jinping II Hydropower Station, China |
title_fullStr | Forecasting and prevention of water inrush during the excavation process of a diversion tunnel at the Jinping II Hydropower Station, China |
title_full_unstemmed | Forecasting and prevention of water inrush during the excavation process of a diversion tunnel at the Jinping II Hydropower Station, China |
title_short | Forecasting and prevention of water inrush during the excavation process of a diversion tunnel at the Jinping II Hydropower Station, China |
title_sort | forecasting and prevention of water inrush during the excavation process of a diversion tunnel at the jinping ii hydropower station, china |
topic | Case Study |
url | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC4899345/ https://www.ncbi.nlm.nih.gov/pubmed/27347472 http://dx.doi.org/10.1186/s40064-016-2336-9 |
work_keys_str_mv | AT houtianxing forecastingandpreventionofwaterinrushduringtheexcavationprocessofadiversiontunnelatthejinpingiihydropowerstationchina AT yangxingguo forecastingandpreventionofwaterinrushduringtheexcavationprocessofadiversiontunnelatthejinpingiihydropowerstationchina AT xinghuige forecastingandpreventionofwaterinrushduringtheexcavationprocessofadiversiontunnelatthejinpingiihydropowerstationchina AT huangkangxin forecastingandpreventionofwaterinrushduringtheexcavationprocessofadiversiontunnelatthejinpingiihydropowerstationchina AT zhoujiawen forecastingandpreventionofwaterinrushduringtheexcavationprocessofadiversiontunnelatthejinpingiihydropowerstationchina |