Dynamic bottleneck elimination in mattress manufacturing line using theory of constraints

There is a tough competition in the furniture sector like other sectors. Along with the varying product range, production system should also be renewed on a regular basis and the production costs should be kept under control. In this study, spring mattress manufacturing line of a furniture manufactu...

Descripción completa

Detalles Bibliográficos
Autores principales: Gundogar, Emin, Sari, Murat, Kokcam, Abdullah H.
Formato: Online Artículo Texto
Lenguaje:English
Publicado: Springer International Publishing 2016
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC4977234/
https://www.ncbi.nlm.nih.gov/pubmed/27547651
http://dx.doi.org/10.1186/s40064-016-2947-1
_version_ 1782446990065401856
author Gundogar, Emin
Sari, Murat
Kokcam, Abdullah H.
author_facet Gundogar, Emin
Sari, Murat
Kokcam, Abdullah H.
author_sort Gundogar, Emin
collection PubMed
description There is a tough competition in the furniture sector like other sectors. Along with the varying product range, production system should also be renewed on a regular basis and the production costs should be kept under control. In this study, spring mattress manufacturing line of a furniture manufacturing company is analyzed. The company wants to increase its production output with new investments. The objective is to find the bottlenecks in production line in order to balance the semi-finished material flow. These bottlenecks are investigated and several different scenarios are tested to improve the current manufacturing system. The problem with a main theme based on the elimination of the bottleneck is solved using Goldratt and Cox’s theory of constraints with a simulation based heuristic method. Near optimal alternatives are determined by system models built in Arena 13.5 simulation software. Results show that approximately 46 % capacity enhancements with 2 buffer stocks have increased average production by 88.8 %.
format Online
Article
Text
id pubmed-4977234
institution National Center for Biotechnology Information
language English
publishDate 2016
publisher Springer International Publishing
record_format MEDLINE/PubMed
spelling pubmed-49772342016-08-19 Dynamic bottleneck elimination in mattress manufacturing line using theory of constraints Gundogar, Emin Sari, Murat Kokcam, Abdullah H. Springerplus Research There is a tough competition in the furniture sector like other sectors. Along with the varying product range, production system should also be renewed on a regular basis and the production costs should be kept under control. In this study, spring mattress manufacturing line of a furniture manufacturing company is analyzed. The company wants to increase its production output with new investments. The objective is to find the bottlenecks in production line in order to balance the semi-finished material flow. These bottlenecks are investigated and several different scenarios are tested to improve the current manufacturing system. The problem with a main theme based on the elimination of the bottleneck is solved using Goldratt and Cox’s theory of constraints with a simulation based heuristic method. Near optimal alternatives are determined by system models built in Arena 13.5 simulation software. Results show that approximately 46 % capacity enhancements with 2 buffer stocks have increased average production by 88.8 %. Springer International Publishing 2016-08-08 /pmc/articles/PMC4977234/ /pubmed/27547651 http://dx.doi.org/10.1186/s40064-016-2947-1 Text en © The Author(s) 2016 Open AccessThis article is distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution, and reproduction in any medium, provided you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons license, and indicate if changes were made.
spellingShingle Research
Gundogar, Emin
Sari, Murat
Kokcam, Abdullah H.
Dynamic bottleneck elimination in mattress manufacturing line using theory of constraints
title Dynamic bottleneck elimination in mattress manufacturing line using theory of constraints
title_full Dynamic bottleneck elimination in mattress manufacturing line using theory of constraints
title_fullStr Dynamic bottleneck elimination in mattress manufacturing line using theory of constraints
title_full_unstemmed Dynamic bottleneck elimination in mattress manufacturing line using theory of constraints
title_short Dynamic bottleneck elimination in mattress manufacturing line using theory of constraints
title_sort dynamic bottleneck elimination in mattress manufacturing line using theory of constraints
topic Research
url https://www.ncbi.nlm.nih.gov/pmc/articles/PMC4977234/
https://www.ncbi.nlm.nih.gov/pubmed/27547651
http://dx.doi.org/10.1186/s40064-016-2947-1
work_keys_str_mv AT gundogaremin dynamicbottleneckeliminationinmattressmanufacturinglineusingtheoryofconstraints
AT sarimurat dynamicbottleneckeliminationinmattressmanufacturinglineusingtheoryofconstraints
AT kokcamabdullahh dynamicbottleneckeliminationinmattressmanufacturinglineusingtheoryofconstraints