A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction

A poor quality affects project makespan and its total costs negatively, but it can be recovered by repair works during construction. We construct a new non-linear programming model based on the classic multi-mode resource constrained project scheduling problem considering repair works. In order to o...

Descripción completa

Detalles Bibliográficos
Autores principales: Fu, Fang, Zhang, Tao
Formato: Online Artículo Texto
Lenguaje:English
Publicado: Public Library of Science 2016
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC5135070/
https://www.ncbi.nlm.nih.gov/pubmed/27911939
http://dx.doi.org/10.1371/journal.pone.0167142
_version_ 1782471566096859136
author Fu, Fang
Zhang, Tao
author_facet Fu, Fang
Zhang, Tao
author_sort Fu, Fang
collection PubMed
description A poor quality affects project makespan and its total costs negatively, but it can be recovered by repair works during construction. We construct a new non-linear programming model based on the classic multi-mode resource constrained project scheduling problem considering repair works. In order to obtain satisfactory quality without a high increase of project cost, the objective is to minimize total quality cost which consists of the prevention cost and failure cost according to Quality-Cost Analysis. A binary dependent normal distribution function is adopted to describe the activity quality; Cumulative quality is defined to determine whether to initiate repair works, according to the different relationships among activity qualities, namely, the coordinative and precedence relationship. Furthermore, a shuffled frog-leaping algorithm is developed to solve this discrete trade-off problem based on an adaptive serial schedule generation scheme and adjusted activity list. In the program of the algorithm, the frog-leaping progress combines the crossover operator of genetic algorithm and a permutation-based local search. Finally, an example of a construction project for a framed railway overpass is provided to examine the algorithm performance, and it assist in decision making to search for the appropriate makespan and quality threshold with minimal cost.
format Online
Article
Text
id pubmed-5135070
institution National Center for Biotechnology Information
language English
publishDate 2016
publisher Public Library of Science
record_format MEDLINE/PubMed
spelling pubmed-51350702016-12-21 A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction Fu, Fang Zhang, Tao PLoS One Research Article A poor quality affects project makespan and its total costs negatively, but it can be recovered by repair works during construction. We construct a new non-linear programming model based on the classic multi-mode resource constrained project scheduling problem considering repair works. In order to obtain satisfactory quality without a high increase of project cost, the objective is to minimize total quality cost which consists of the prevention cost and failure cost according to Quality-Cost Analysis. A binary dependent normal distribution function is adopted to describe the activity quality; Cumulative quality is defined to determine whether to initiate repair works, according to the different relationships among activity qualities, namely, the coordinative and precedence relationship. Furthermore, a shuffled frog-leaping algorithm is developed to solve this discrete trade-off problem based on an adaptive serial schedule generation scheme and adjusted activity list. In the program of the algorithm, the frog-leaping progress combines the crossover operator of genetic algorithm and a permutation-based local search. Finally, an example of a construction project for a framed railway overpass is provided to examine the algorithm performance, and it assist in decision making to search for the appropriate makespan and quality threshold with minimal cost. Public Library of Science 2016-12-02 /pmc/articles/PMC5135070/ /pubmed/27911939 http://dx.doi.org/10.1371/journal.pone.0167142 Text en © 2016 Fu, Zhang http://creativecommons.org/licenses/by/4.0/ This is an open access article distributed under the terms of the Creative Commons Attribution License (http://creativecommons.org/licenses/by/4.0/) , which permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited.
spellingShingle Research Article
Fu, Fang
Zhang, Tao
A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction
title A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction
title_full A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction
title_fullStr A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction
title_full_unstemmed A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction
title_short A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction
title_sort new model for solving time-cost-quality trade-off problems in construction
topic Research Article
url https://www.ncbi.nlm.nih.gov/pmc/articles/PMC5135070/
https://www.ncbi.nlm.nih.gov/pubmed/27911939
http://dx.doi.org/10.1371/journal.pone.0167142
work_keys_str_mv AT fufang anewmodelforsolvingtimecostqualitytradeoffproblemsinconstruction
AT zhangtao anewmodelforsolvingtimecostqualitytradeoffproblemsinconstruction
AT fufang newmodelforsolvingtimecostqualitytradeoffproblemsinconstruction
AT zhangtao newmodelforsolvingtimecostqualitytradeoffproblemsinconstruction