Why the vision of interregional electric transmission development in FERC Order 1000 is not happening

The Federal Energy Regulatory Commission (FERC) on March 19, 2020 announced a Notice of Proposed Rulemaking (NOPR) to further investigate how financial incentives might be used to encourage development of high-voltage electric transmission in the United States. An extension of previous efforts in FE...

Descripción completa

Detalles Bibliográficos
Autores principales: Schulte, Robert H., Fletcher, Fredric C.
Formato: Online Artículo Texto
Lenguaje:English
Publicado: Elsevier Inc. 2020
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC7194651/
http://dx.doi.org/10.1016/j.tej.2020.106773
_version_ 1783528382508564480
author Schulte, Robert H.
Fletcher, Fredric C.
author_facet Schulte, Robert H.
Fletcher, Fredric C.
author_sort Schulte, Robert H.
collection PubMed
description The Federal Energy Regulatory Commission (FERC) on March 19, 2020 announced a Notice of Proposed Rulemaking (NOPR) to further investigate how financial incentives might be used to encourage development of high-voltage electric transmission in the United States. An extension of previous efforts in FERC Order 679 issued in 2006, the NOPR-proposed incentives would consist of up to 250 additional basis points of equity return to be allowed on qualifying transmission projects. The NOPR was published in the Federal Register on April 2, and public comments were due back to FERC by July 1. Such incentives, if adopted, would be helpful to address prior FERC business that is yet undone. Issued in 2011, FERC Order 1000, “Transmission and Cost Allocation by Transmission Owning and Operating Utilities” among other things envisioned coordinated planning of interregional transmission developments spanning between individual Regional Transmission Organizations (RTO) and Independent System Operators (ISO), the operators of the FERC-regulated organized wholesale markets. In addition to traditional goals of generator interconnection and service reliability, the purpose of such interregional transmission development was to support public policy goals including renewable energy development, and lower costs for consumers. But little or no such interregional development has happened since Order 1000. Why? The authors have spent the last several years promoting development of one such interregional transmission project. While the effort is ongoing, the on-the-ground experience to-date clearly shows the reasons why interregional development envisioned by FERC Order 1000 is not happening. The authors offer solutions to the issues, including how the new FERC NOPR for transmission incentives can be helpful.
format Online
Article
Text
id pubmed-7194651
institution National Center for Biotechnology Information
language English
publishDate 2020
publisher Elsevier Inc.
record_format MEDLINE/PubMed
spelling pubmed-71946512020-05-02 Why the vision of interregional electric transmission development in FERC Order 1000 is not happening Schulte, Robert H. Fletcher, Fredric C. The Electricity Journal Article The Federal Energy Regulatory Commission (FERC) on March 19, 2020 announced a Notice of Proposed Rulemaking (NOPR) to further investigate how financial incentives might be used to encourage development of high-voltage electric transmission in the United States. An extension of previous efforts in FERC Order 679 issued in 2006, the NOPR-proposed incentives would consist of up to 250 additional basis points of equity return to be allowed on qualifying transmission projects. The NOPR was published in the Federal Register on April 2, and public comments were due back to FERC by July 1. Such incentives, if adopted, would be helpful to address prior FERC business that is yet undone. Issued in 2011, FERC Order 1000, “Transmission and Cost Allocation by Transmission Owning and Operating Utilities” among other things envisioned coordinated planning of interregional transmission developments spanning between individual Regional Transmission Organizations (RTO) and Independent System Operators (ISO), the operators of the FERC-regulated organized wholesale markets. In addition to traditional goals of generator interconnection and service reliability, the purpose of such interregional transmission development was to support public policy goals including renewable energy development, and lower costs for consumers. But little or no such interregional development has happened since Order 1000. Why? The authors have spent the last several years promoting development of one such interregional transmission project. While the effort is ongoing, the on-the-ground experience to-date clearly shows the reasons why interregional development envisioned by FERC Order 1000 is not happening. The authors offer solutions to the issues, including how the new FERC NOPR for transmission incentives can be helpful. Elsevier Inc. 2020-07 2020-04-24 /pmc/articles/PMC7194651/ http://dx.doi.org/10.1016/j.tej.2020.106773 Text en © 2020 Elsevier Inc. All rights reserved. Since January 2020 Elsevier has created a COVID-19 resource centre with free information in English and Mandarin on the novel coronavirus COVID-19. The COVID-19 resource centre is hosted on Elsevier Connect, the company's public news and information website. Elsevier hereby grants permission to make all its COVID-19-related research that is available on the COVID-19 resource centre - including this research content - immediately available in PubMed Central and other publicly funded repositories, such as the WHO COVID database with rights for unrestricted research re-use and analyses in any form or by any means with acknowledgement of the original source. These permissions are granted for free by Elsevier for as long as the COVID-19 resource centre remains active.
spellingShingle Article
Schulte, Robert H.
Fletcher, Fredric C.
Why the vision of interregional electric transmission development in FERC Order 1000 is not happening
title Why the vision of interregional electric transmission development in FERC Order 1000 is not happening
title_full Why the vision of interregional electric transmission development in FERC Order 1000 is not happening
title_fullStr Why the vision of interregional electric transmission development in FERC Order 1000 is not happening
title_full_unstemmed Why the vision of interregional electric transmission development in FERC Order 1000 is not happening
title_short Why the vision of interregional electric transmission development in FERC Order 1000 is not happening
title_sort why the vision of interregional electric transmission development in ferc order 1000 is not happening
topic Article
url https://www.ncbi.nlm.nih.gov/pmc/articles/PMC7194651/
http://dx.doi.org/10.1016/j.tej.2020.106773
work_keys_str_mv AT schulteroberth whythevisionofinterregionalelectrictransmissiondevelopmentinfercorder1000isnothappening
AT fletcherfredricc whythevisionofinterregionalelectrictransmissiondevelopmentinfercorder1000isnothappening