Proactive Scheduling and Reactive Real-Time Control in Industry 4.0

Scheduling in Industry 4.0 systems belongs to a class of problems that have mixed structural-temporal-logical constraints. In other words, a strong coupling is considered when product and process are created simultaneously. As a result of the proven NP-hardness of such problems, solution methods hav...

Descripción completa

Detalles Bibliográficos
Autores principales: Ivanov, Dmitry, Sokolov, Boris, Werner, Frank, Dolgui, Alexandre
Formato: Online Artículo Texto
Lenguaje:English
Publicado: 2020
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC7279436/
http://dx.doi.org/10.1007/978-3-030-43177-8_2
_version_ 1783543561497608192
author Ivanov, Dmitry
Sokolov, Boris
Werner, Frank
Dolgui, Alexandre
author_facet Ivanov, Dmitry
Sokolov, Boris
Werner, Frank
Dolgui, Alexandre
author_sort Ivanov, Dmitry
collection PubMed
description Scheduling in Industry 4.0 systems belongs to a class of problems that have mixed structural-temporal-logical constraints. In other words, a strong coupling is considered when product and process are created simultaneously. As a result of the proven NP-hardness of such problems, solution methods have extensively utilized different decomposition principles. The known decomposition methods in discrete optimization are founded on the difficulties in deriving analytical properties. The existing solutions in continuous optimization are based on the maximum principle and yield a dynamic process decomposition using the natural logic of time. By combining the advantages of continuous and discrete optimization, this chapter develops a decomposition method for shop floor scheduling in Industry 4.0 manufacturing systems. Technically, this study proposes to decompose dynamically the large-scale assignment matrix according to the precedence relations between the operations of the jobs and considers only the operations that satisfy these precedence relations at a given time point in small-dimensional, discrete optimization models. Continuous optimization is used to generate a schedule from the assignments found in the discrete optimization models at each time point by extremizing the Hamiltonian function at this time point subject to scheduling objective(s). In addition, the execution of the operations in time can be accurately modeled in continuous time as a continuous state variable; the machine availability and capacity disturbances at the machines are also considered. The method developed provides further insights into decomposition methods for scheduling and is supported by an analytical analysis and an algorithmic realization.
format Online
Article
Text
id pubmed-7279436
institution National Center for Biotechnology Information
language English
publishDate 2020
record_format MEDLINE/PubMed
spelling pubmed-72794362020-06-09 Proactive Scheduling and Reactive Real-Time Control in Industry 4.0 Ivanov, Dmitry Sokolov, Boris Werner, Frank Dolgui, Alexandre Scheduling in Industry 4.0 and Cloud Manufacturing Article Scheduling in Industry 4.0 systems belongs to a class of problems that have mixed structural-temporal-logical constraints. In other words, a strong coupling is considered when product and process are created simultaneously. As a result of the proven NP-hardness of such problems, solution methods have extensively utilized different decomposition principles. The known decomposition methods in discrete optimization are founded on the difficulties in deriving analytical properties. The existing solutions in continuous optimization are based on the maximum principle and yield a dynamic process decomposition using the natural logic of time. By combining the advantages of continuous and discrete optimization, this chapter develops a decomposition method for shop floor scheduling in Industry 4.0 manufacturing systems. Technically, this study proposes to decompose dynamically the large-scale assignment matrix according to the precedence relations between the operations of the jobs and considers only the operations that satisfy these precedence relations at a given time point in small-dimensional, discrete optimization models. Continuous optimization is used to generate a schedule from the assignments found in the discrete optimization models at each time point by extremizing the Hamiltonian function at this time point subject to scheduling objective(s). In addition, the execution of the operations in time can be accurately modeled in continuous time as a continuous state variable; the machine availability and capacity disturbances at the machines are also considered. The method developed provides further insights into decomposition methods for scheduling and is supported by an analytical analysis and an algorithmic realization. 2020-06-09 /pmc/articles/PMC7279436/ http://dx.doi.org/10.1007/978-3-030-43177-8_2 Text en © Springer Nature Switzerland AG 2020 This article is made available via the PMC Open Access Subset for unrestricted research re-use and secondary analysis in any form or by any means with acknowledgement of the original source. These permissions are granted for the duration of the World Health Organization (WHO) declaration of COVID-19 as a global pandemic.
spellingShingle Article
Ivanov, Dmitry
Sokolov, Boris
Werner, Frank
Dolgui, Alexandre
Proactive Scheduling and Reactive Real-Time Control in Industry 4.0
title Proactive Scheduling and Reactive Real-Time Control in Industry 4.0
title_full Proactive Scheduling and Reactive Real-Time Control in Industry 4.0
title_fullStr Proactive Scheduling and Reactive Real-Time Control in Industry 4.0
title_full_unstemmed Proactive Scheduling and Reactive Real-Time Control in Industry 4.0
title_short Proactive Scheduling and Reactive Real-Time Control in Industry 4.0
title_sort proactive scheduling and reactive real-time control in industry 4.0
topic Article
url https://www.ncbi.nlm.nih.gov/pmc/articles/PMC7279436/
http://dx.doi.org/10.1007/978-3-030-43177-8_2
work_keys_str_mv AT ivanovdmitry proactiveschedulingandreactiverealtimecontrolinindustry40
AT sokolovboris proactiveschedulingandreactiverealtimecontrolinindustry40
AT wernerfrank proactiveschedulingandreactiverealtimecontrolinindustry40
AT dolguialexandre proactiveschedulingandreactiverealtimecontrolinindustry40