On-load measurement method for the reliability of distribution transformers
Transformer is the most important equipment used in power system. It's ensure network stability and reliability. Transformer fails over time due to several factors such as overload, poor insulation, cellulose deterioration, poor dielectric strength of the oil etc. However, transformer owners ar...
Autores principales: | , , , |
---|---|
Formato: | Online Artículo Texto |
Lenguaje: | English |
Publicado: |
Elsevier
2020
|
Materias: | |
Acceso en línea: | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC7586130/ https://www.ncbi.nlm.nih.gov/pubmed/33134095 http://dx.doi.org/10.1016/j.mex.2020.101089 |
_version_ | 1783599933676322816 |
---|---|
author | Adesina, Lambe Mutalub Abdulkareem, Ademola Ogunbiyi, Olalekan Ibrahim, Oladimeji |
author_facet | Adesina, Lambe Mutalub Abdulkareem, Ademola Ogunbiyi, Olalekan Ibrahim, Oladimeji |
author_sort | Adesina, Lambe Mutalub |
collection | PubMed |
description | Transformer is the most important equipment used in power system. It's ensure network stability and reliability. Transformer fails over time due to several factors such as overload, poor insulation, cellulose deterioration, poor dielectric strength of the oil etc. However, transformer owners are finding it difficult to monitor the performance of distribution transformers (DT) in their place of application which results to system failure. Analyses of this distribution transformer performance required that distribution transformer be put on-load and the secondary terminals link to Power Quality and Energy Analyzer equipment (Fluke 435 Series II). This paper presents a methodology of carrying out experimental set up of on-load reliability measurements of the two distribution transformers, 500 kVA and 300 kVA, 11/0.415 kV as case study. Recommendations for the operations and maintenance engineers in charge to comply are discussed. This approach using the prescribed power quality equipment gives a reliable experimental method of evaluating the performance of distribution transformers. • Maintaining the selected distribution transformer on – load prior to and during the experiment. • The setting of experimental circuit to determine the operational parameters involving DT connection to Power Quality and Energy Analyzer (PQEA) equipment. • It utilize personal computer to download the measured parameters for graphical and statistics analysis. |
format | Online Article Text |
id | pubmed-7586130 |
institution | National Center for Biotechnology Information |
language | English |
publishDate | 2020 |
publisher | Elsevier |
record_format | MEDLINE/PubMed |
spelling | pubmed-75861302020-10-30 On-load measurement method for the reliability of distribution transformers Adesina, Lambe Mutalub Abdulkareem, Ademola Ogunbiyi, Olalekan Ibrahim, Oladimeji MethodsX Method Article Transformer is the most important equipment used in power system. It's ensure network stability and reliability. Transformer fails over time due to several factors such as overload, poor insulation, cellulose deterioration, poor dielectric strength of the oil etc. However, transformer owners are finding it difficult to monitor the performance of distribution transformers (DT) in their place of application which results to system failure. Analyses of this distribution transformer performance required that distribution transformer be put on-load and the secondary terminals link to Power Quality and Energy Analyzer equipment (Fluke 435 Series II). This paper presents a methodology of carrying out experimental set up of on-load reliability measurements of the two distribution transformers, 500 kVA and 300 kVA, 11/0.415 kV as case study. Recommendations for the operations and maintenance engineers in charge to comply are discussed. This approach using the prescribed power quality equipment gives a reliable experimental method of evaluating the performance of distribution transformers. • Maintaining the selected distribution transformer on – load prior to and during the experiment. • The setting of experimental circuit to determine the operational parameters involving DT connection to Power Quality and Energy Analyzer (PQEA) equipment. • It utilize personal computer to download the measured parameters for graphical and statistics analysis. Elsevier 2020-10-09 /pmc/articles/PMC7586130/ /pubmed/33134095 http://dx.doi.org/10.1016/j.mex.2020.101089 Text en © 2020 The Authors http://creativecommons.org/licenses/by/4.0/ This is an open access article under the CC BY license (http://creativecommons.org/licenses/by/4.0/). |
spellingShingle | Method Article Adesina, Lambe Mutalub Abdulkareem, Ademola Ogunbiyi, Olalekan Ibrahim, Oladimeji On-load measurement method for the reliability of distribution transformers |
title | On-load measurement method for the reliability of distribution transformers |
title_full | On-load measurement method for the reliability of distribution transformers |
title_fullStr | On-load measurement method for the reliability of distribution transformers |
title_full_unstemmed | On-load measurement method for the reliability of distribution transformers |
title_short | On-load measurement method for the reliability of distribution transformers |
title_sort | on-load measurement method for the reliability of distribution transformers |
topic | Method Article |
url | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC7586130/ https://www.ncbi.nlm.nih.gov/pubmed/33134095 http://dx.doi.org/10.1016/j.mex.2020.101089 |
work_keys_str_mv | AT adesinalambemutalub onloadmeasurementmethodforthereliabilityofdistributiontransformers AT abdulkareemademola onloadmeasurementmethodforthereliabilityofdistributiontransformers AT ogunbiyiolalekan onloadmeasurementmethodforthereliabilityofdistributiontransformers AT ibrahimoladimeji onloadmeasurementmethodforthereliabilityofdistributiontransformers |