Research on extremely short construction period of engineering project based on labor balance under resource tolerance

Under the condition of resource tolerance, engineering construction projects face the problem of labor force balance in the working face. Notably, a deviation occurs between the distribution and certain demand of the labor force in the limited working face, which affects the realization of an extrem...

Descripción completa

Detalles Bibliográficos
Autores principales: Peng, Junlong, Wang, Mengyao, Peng, Chao, Hu, Ke
Formato: Online Artículo Texto
Lenguaje:English
Publicado: Public Library of Science 2022
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC8967018/
https://www.ncbi.nlm.nih.gov/pubmed/35353862
http://dx.doi.org/10.1371/journal.pone.0266036
_version_ 1784678748437610496
author Peng, Junlong
Wang, Mengyao
Peng, Chao
Hu, Ke
author_facet Peng, Junlong
Wang, Mengyao
Peng, Chao
Hu, Ke
author_sort Peng, Junlong
collection PubMed
description Under the condition of resource tolerance, engineering construction projects face the problem of labor force balance in the working face. Notably, a deviation occurs between the distribution and certain demand of the labor force in the limited working face, which affects the realization of an extremely short construction period. To address this problem, we first introduced the stochastic coefficient of labor force equilibrium to measure the degree of labor balance. Second, a labor force equilibrium model with the realization goal of an extremely short construction period was established. Then, the standard particle swarm optimization (PSO) algorithm was improved from two perspectives to solve the proposed model. The update equation was rounded to solve practical project problems, and a dynamic variable inertia weight was adopted to ensure the PSO algorithm accuracy and convergence speed. Finally, through case analysis, we determined the extremely short construction period and best labor force distribution scheme. Moreover, the case results revealed that the established model is simple, operable and practical and that the proposed algorithm achieves a high search accuracy and efficiency in the model solution process. Overall, under the condition of resource tolerance, this study provides scientific and effective references for managers to realize an extremely short construction period.
format Online
Article
Text
id pubmed-8967018
institution National Center for Biotechnology Information
language English
publishDate 2022
publisher Public Library of Science
record_format MEDLINE/PubMed
spelling pubmed-89670182022-03-31 Research on extremely short construction period of engineering project based on labor balance under resource tolerance Peng, Junlong Wang, Mengyao Peng, Chao Hu, Ke PLoS One Research Article Under the condition of resource tolerance, engineering construction projects face the problem of labor force balance in the working face. Notably, a deviation occurs between the distribution and certain demand of the labor force in the limited working face, which affects the realization of an extremely short construction period. To address this problem, we first introduced the stochastic coefficient of labor force equilibrium to measure the degree of labor balance. Second, a labor force equilibrium model with the realization goal of an extremely short construction period was established. Then, the standard particle swarm optimization (PSO) algorithm was improved from two perspectives to solve the proposed model. The update equation was rounded to solve practical project problems, and a dynamic variable inertia weight was adopted to ensure the PSO algorithm accuracy and convergence speed. Finally, through case analysis, we determined the extremely short construction period and best labor force distribution scheme. Moreover, the case results revealed that the established model is simple, operable and practical and that the proposed algorithm achieves a high search accuracy and efficiency in the model solution process. Overall, under the condition of resource tolerance, this study provides scientific and effective references for managers to realize an extremely short construction period. Public Library of Science 2022-03-30 /pmc/articles/PMC8967018/ /pubmed/35353862 http://dx.doi.org/10.1371/journal.pone.0266036 Text en © 2022 Peng et al https://creativecommons.org/licenses/by/4.0/This is an open access article distributed under the terms of the Creative Commons Attribution License (https://creativecommons.org/licenses/by/4.0/) , which permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited.
spellingShingle Research Article
Peng, Junlong
Wang, Mengyao
Peng, Chao
Hu, Ke
Research on extremely short construction period of engineering project based on labor balance under resource tolerance
title Research on extremely short construction period of engineering project based on labor balance under resource tolerance
title_full Research on extremely short construction period of engineering project based on labor balance under resource tolerance
title_fullStr Research on extremely short construction period of engineering project based on labor balance under resource tolerance
title_full_unstemmed Research on extremely short construction period of engineering project based on labor balance under resource tolerance
title_short Research on extremely short construction period of engineering project based on labor balance under resource tolerance
title_sort research on extremely short construction period of engineering project based on labor balance under resource tolerance
topic Research Article
url https://www.ncbi.nlm.nih.gov/pmc/articles/PMC8967018/
https://www.ncbi.nlm.nih.gov/pubmed/35353862
http://dx.doi.org/10.1371/journal.pone.0266036
work_keys_str_mv AT pengjunlong researchonextremelyshortconstructionperiodofengineeringprojectbasedonlaborbalanceunderresourcetolerance
AT wangmengyao researchonextremelyshortconstructionperiodofengineeringprojectbasedonlaborbalanceunderresourcetolerance
AT pengchao researchonextremelyshortconstructionperiodofengineeringprojectbasedonlaborbalanceunderresourcetolerance
AT huke researchonextremelyshortconstructionperiodofengineeringprojectbasedonlaborbalanceunderresourcetolerance