Research on extremely short construction period of engineering project based on labor balance under resource tolerance
Under the condition of resource tolerance, engineering construction projects face the problem of labor force balance in the working face. Notably, a deviation occurs between the distribution and certain demand of the labor force in the limited working face, which affects the realization of an extrem...
Autores principales: | , , , |
---|---|
Formato: | Online Artículo Texto |
Lenguaje: | English |
Publicado: |
Public Library of Science
2022
|
Materias: | |
Acceso en línea: | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC8967018/ https://www.ncbi.nlm.nih.gov/pubmed/35353862 http://dx.doi.org/10.1371/journal.pone.0266036 |
_version_ | 1784678748437610496 |
---|---|
author | Peng, Junlong Wang, Mengyao Peng, Chao Hu, Ke |
author_facet | Peng, Junlong Wang, Mengyao Peng, Chao Hu, Ke |
author_sort | Peng, Junlong |
collection | PubMed |
description | Under the condition of resource tolerance, engineering construction projects face the problem of labor force balance in the working face. Notably, a deviation occurs between the distribution and certain demand of the labor force in the limited working face, which affects the realization of an extremely short construction period. To address this problem, we first introduced the stochastic coefficient of labor force equilibrium to measure the degree of labor balance. Second, a labor force equilibrium model with the realization goal of an extremely short construction period was established. Then, the standard particle swarm optimization (PSO) algorithm was improved from two perspectives to solve the proposed model. The update equation was rounded to solve practical project problems, and a dynamic variable inertia weight was adopted to ensure the PSO algorithm accuracy and convergence speed. Finally, through case analysis, we determined the extremely short construction period and best labor force distribution scheme. Moreover, the case results revealed that the established model is simple, operable and practical and that the proposed algorithm achieves a high search accuracy and efficiency in the model solution process. Overall, under the condition of resource tolerance, this study provides scientific and effective references for managers to realize an extremely short construction period. |
format | Online Article Text |
id | pubmed-8967018 |
institution | National Center for Biotechnology Information |
language | English |
publishDate | 2022 |
publisher | Public Library of Science |
record_format | MEDLINE/PubMed |
spelling | pubmed-89670182022-03-31 Research on extremely short construction period of engineering project based on labor balance under resource tolerance Peng, Junlong Wang, Mengyao Peng, Chao Hu, Ke PLoS One Research Article Under the condition of resource tolerance, engineering construction projects face the problem of labor force balance in the working face. Notably, a deviation occurs between the distribution and certain demand of the labor force in the limited working face, which affects the realization of an extremely short construction period. To address this problem, we first introduced the stochastic coefficient of labor force equilibrium to measure the degree of labor balance. Second, a labor force equilibrium model with the realization goal of an extremely short construction period was established. Then, the standard particle swarm optimization (PSO) algorithm was improved from two perspectives to solve the proposed model. The update equation was rounded to solve practical project problems, and a dynamic variable inertia weight was adopted to ensure the PSO algorithm accuracy and convergence speed. Finally, through case analysis, we determined the extremely short construction period and best labor force distribution scheme. Moreover, the case results revealed that the established model is simple, operable and practical and that the proposed algorithm achieves a high search accuracy and efficiency in the model solution process. Overall, under the condition of resource tolerance, this study provides scientific and effective references for managers to realize an extremely short construction period. Public Library of Science 2022-03-30 /pmc/articles/PMC8967018/ /pubmed/35353862 http://dx.doi.org/10.1371/journal.pone.0266036 Text en © 2022 Peng et al https://creativecommons.org/licenses/by/4.0/This is an open access article distributed under the terms of the Creative Commons Attribution License (https://creativecommons.org/licenses/by/4.0/) , which permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited. |
spellingShingle | Research Article Peng, Junlong Wang, Mengyao Peng, Chao Hu, Ke Research on extremely short construction period of engineering project based on labor balance under resource tolerance |
title | Research on extremely short construction period of engineering project based on labor balance under resource tolerance |
title_full | Research on extremely short construction period of engineering project based on labor balance under resource tolerance |
title_fullStr | Research on extremely short construction period of engineering project based on labor balance under resource tolerance |
title_full_unstemmed | Research on extremely short construction period of engineering project based on labor balance under resource tolerance |
title_short | Research on extremely short construction period of engineering project based on labor balance under resource tolerance |
title_sort | research on extremely short construction period of engineering project based on labor balance under resource tolerance |
topic | Research Article |
url | https://www.ncbi.nlm.nih.gov/pmc/articles/PMC8967018/ https://www.ncbi.nlm.nih.gov/pubmed/35353862 http://dx.doi.org/10.1371/journal.pone.0266036 |
work_keys_str_mv | AT pengjunlong researchonextremelyshortconstructionperiodofengineeringprojectbasedonlaborbalanceunderresourcetolerance AT wangmengyao researchonextremelyshortconstructionperiodofengineeringprojectbasedonlaborbalanceunderresourcetolerance AT pengchao researchonextremelyshortconstructionperiodofengineeringprojectbasedonlaborbalanceunderresourcetolerance AT huke researchonextremelyshortconstructionperiodofengineeringprojectbasedonlaborbalanceunderresourcetolerance |