Critical delay factors for construction projects in Central Aceh District, Indonesia

Background: Construction development in Indonesia is growing rapidly, especially in Central Aceh District. Construction projects often experience risks, so that risk events can have a serious impact on the viability of the project. Project delays can result in cost overruns and project losses. There...

Descripción completa

Detalles Bibliográficos
Autores principales: Rauzana, Anita, Zahrah, Aghnia, Dharma, Wira
Formato: Online Artículo Texto
Lenguaje:English
Publicado: F1000 Research Limited 2022
Materias:
Acceso en línea:https://www.ncbi.nlm.nih.gov/pmc/articles/PMC9860196/
https://www.ncbi.nlm.nih.gov/pubmed/36704049
http://dx.doi.org/10.12688/f1000research.110024.3
_version_ 1784874526115364864
author Rauzana, Anita
Zahrah, Aghnia
Dharma, Wira
author_facet Rauzana, Anita
Zahrah, Aghnia
Dharma, Wira
author_sort Rauzana, Anita
collection PubMed
description Background: Construction development in Indonesia is growing rapidly, especially in Central Aceh District. Construction projects often experience risks, so that risk events can have a serious impact on the viability of the project. Project delays can result in cost overruns and project losses. Therefore, it is necessary to identify the factors causing project delays.The purpose of this study was to (1) identify the risk factors that cause delays in construction projects and (2) determine those particular risk factors that have a greater influence on construction projects. The location of this research was Central Aceh District. Methods: The data in this study were primary data in the form of a questionnaire and secondary data obtained from the literature related to this particular type of research. Questionnaires were distributed to respondents, namely contractor companies located in the Central Aceh District. The questionnaires were distributed to determine respondents' opinions about the level of influence of risk factors causing project delays. We used a validity test, reliability test, and descriptive analysis for data processing. Results: Based on the results of the study from 47 respondents, the “very high influence” category (Mode=5) for the tool malfunction factor, cost estimation inaccuracy, increased work costs, implementation of new technologies, details, accuracy and conformity to specifications that are not appropriate, worker quarrels, poor project planning and management, poor condition at locations and accessibility difficulty. Conclusions: Of the 80 risk factors that caused project delays, eight risk factors were found to have a very high influence on the implementation of construction projects in Central Aceh District. Practical implications: The results of this study provide knowledge to contractor companies about the delay factors that have the most influence on project implementation so that they are expected to be able to manage risks to avoid losses.
format Online
Article
Text
id pubmed-9860196
institution National Center for Biotechnology Information
language English
publishDate 2022
publisher F1000 Research Limited
record_format MEDLINE/PubMed
spelling pubmed-98601962023-01-25 Critical delay factors for construction projects in Central Aceh District, Indonesia Rauzana, Anita Zahrah, Aghnia Dharma, Wira F1000Res Research Article Background: Construction development in Indonesia is growing rapidly, especially in Central Aceh District. Construction projects often experience risks, so that risk events can have a serious impact on the viability of the project. Project delays can result in cost overruns and project losses. Therefore, it is necessary to identify the factors causing project delays.The purpose of this study was to (1) identify the risk factors that cause delays in construction projects and (2) determine those particular risk factors that have a greater influence on construction projects. The location of this research was Central Aceh District. Methods: The data in this study were primary data in the form of a questionnaire and secondary data obtained from the literature related to this particular type of research. Questionnaires were distributed to respondents, namely contractor companies located in the Central Aceh District. The questionnaires were distributed to determine respondents' opinions about the level of influence of risk factors causing project delays. We used a validity test, reliability test, and descriptive analysis for data processing. Results: Based on the results of the study from 47 respondents, the “very high influence” category (Mode=5) for the tool malfunction factor, cost estimation inaccuracy, increased work costs, implementation of new technologies, details, accuracy and conformity to specifications that are not appropriate, worker quarrels, poor project planning and management, poor condition at locations and accessibility difficulty. Conclusions: Of the 80 risk factors that caused project delays, eight risk factors were found to have a very high influence on the implementation of construction projects in Central Aceh District. Practical implications: The results of this study provide knowledge to contractor companies about the delay factors that have the most influence on project implementation so that they are expected to be able to manage risks to avoid losses. F1000 Research Limited 2022-09-29 /pmc/articles/PMC9860196/ /pubmed/36704049 http://dx.doi.org/10.12688/f1000research.110024.3 Text en Copyright: © 2022 Rauzana A et al. https://creativecommons.org/licenses/by/4.0/This is an open access article distributed under the terms of the Creative Commons Attribution Licence, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
spellingShingle Research Article
Rauzana, Anita
Zahrah, Aghnia
Dharma, Wira
Critical delay factors for construction projects in Central Aceh District, Indonesia
title Critical delay factors for construction projects in Central Aceh District, Indonesia
title_full Critical delay factors for construction projects in Central Aceh District, Indonesia
title_fullStr Critical delay factors for construction projects in Central Aceh District, Indonesia
title_full_unstemmed Critical delay factors for construction projects in Central Aceh District, Indonesia
title_short Critical delay factors for construction projects in Central Aceh District, Indonesia
title_sort critical delay factors for construction projects in central aceh district, indonesia
topic Research Article
url https://www.ncbi.nlm.nih.gov/pmc/articles/PMC9860196/
https://www.ncbi.nlm.nih.gov/pubmed/36704049
http://dx.doi.org/10.12688/f1000research.110024.3
work_keys_str_mv AT rauzanaanita criticaldelayfactorsforconstructionprojectsincentralacehdistrictindonesia
AT zahrahaghnia criticaldelayfactorsforconstructionprojectsincentralacehdistrictindonesia
AT dharmawira criticaldelayfactorsforconstructionprojectsincentralacehdistrictindonesia