Cargando…

Beam Commissioning of the SPS-to-LHC Transfer Line TI 2

The transfer line for the LHC Ring 1 was successfully commissioned with beam in the autumn of 2007. After extraction from the SPS accelerator and about 2.7 km of new transfer line, the beam arrived at the temporarily installed beam dump, about 50 m before the start of the LHC tunnel, without the nee...

Descripción completa

Detalles Bibliográficos
Autores principales: Uythoven, J, Arduini, Gianluigi, Assmann, Ralph Wolfgang, Gilbert, N, Goddard, B, Kain, V, Koschik, A, Kramer, T, Lamont, M, Mertens, V, Redaelli, R, Wenninger, J
Lenguaje:eng
Publicado: 2008
Materias:
Acceso en línea:http://cds.cern.ch/record/1123694