Operational experience with circulating beam
Following various injection tests, the full LHC beam commissioning started on September 10th. Within three days of beam operation, we established stable and captured circulating beam 2 and achieved circulating beam 1 for many turns. This was made possible by a thorough preparations of all the requir...