MD 2935: 16L2 solenoid tests
This MD allowed confirming that the solenoid installed in 16L2 during Technical Stop 2 (TS22017) could be held responsible for the performance improvement observed after TS2. The MD was performed on 30th November 2017 in parallel with MD#2889 and the procedure was adjusted for both MDs to profit as...